description abstract | Much of the project scheduling literature treats task durations as deterministic. In reality, however, task durations are subject to considerable uncertainty, and that uncertainty can be influenced by the resources assigned. The purpose of this paper is to provide the means for contractors to optimally allocate their skilled workers among individual tasks for a single project. Instead of the traditional use of | |
publisher | American Society of Civil Engineers | |
title | Project Planning for Construction under Uncertainty with Limited Resources | |
type | Journal Paper | |
journal volume | 133 | |
journal issue | 4 | |
journal title | Journal of Construction Engineering and Management | |
identifier doi | 10.1061/(ASCE)0733-9364(2007)133:4(268) | |
tree | Journal of Construction Engineering and Management:;2007:;Volume ( 133 ):;issue: 004 | |
contenttype | Fulltext | |