Abstract: The Atucha II nuclear power plant is a unique pressurized heavy water reactor (PHWR) being constructed in Argentina. The original plant design was by Kraftwerk Union (KWU) in the 1970's using the German methodology of break preclusion. The plant construction was halted for several decades, but a recent need for power was the driver for restarting the construction. The United States Nuclear Regulatory Commission (US NRC) developed leakbeforebreak (LBB) procedures in standard review plan (SRP) 3.6.3 Revision 1 for the purpose of eliminating the need to design for dynamic effects that allowed the elimination of pipe whip restraints and jet impingement shields. This SRP was originally written in 1987. The US NRC is currently developing a draft Regulatory Guide on what is called the transition break size (TBS). However, modeling crack pipe response in large complex primary piping systems under seismic loading is a difficult analysis challenge due to many factors. The initial published work (Wilkowski et al., “Robust LBB Analysis for Atucha II Nuclear Plant,†2011 ASME PVP Conference, July 17–21, Baltimore, MD) on the seismic evaluations for the Atucha II plant showed that even with a seismic event with the amplitudes corresponding to the amplitudes for an event with a probability of 1 أ— 10−6 per year, that a doubleended guillotine break (DEGB) was pragmatically impossible due to the high leakage rates and total loss of makeup water inventory. The critical circumferential throughwall flaw size in that case was 94% of the circumference. This paper discusses further efforts to show how much higher the applied accelerations would have to be to cause a DEGB for an initial circumferential throughwall crack that was 33% around the circumference. This flaw length would also be easily detected by leakage and loss of makeup water inventory. These analyses showed that the applied seismic peakground accelerations had to exceed 25 g's for the case of this throughwallcrack to become a DEGB during a single seismic loading event. This is a factor of 80 times higher than the 1 أ— 10−6 seismic event accelerations, or 240 times higher than the safe shutdown earthquake (SSE) accelerations.
|
Collections
Show full item record
| contributor author | Zhang, Tao | |
| contributor author | Brust, Frederick W. | |
| contributor author | Wilkowski, Gery | |
| contributor author | Xu, Heqin | |
| contributor author | Betervide, Alfredo A. | |
| contributor author | Mazzantini, Oscar | |
| date accessioned | 2017-05-09T01:02:27Z | |
| date available | 2017-05-09T01:02:27Z | |
| date issued | 2013 | |
| identifier issn | 0094-9930 | |
| identifier other | pvt_135_05_051801.pdf | |
| identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/153095 | |
| description abstract | The Atucha II nuclear power plant is a unique pressurized heavy water reactor (PHWR) being constructed in Argentina. The original plant design was by Kraftwerk Union (KWU) in the 1970's using the German methodology of break preclusion. The plant construction was halted for several decades, but a recent need for power was the driver for restarting the construction. The United States Nuclear Regulatory Commission (US NRC) developed leakbeforebreak (LBB) procedures in standard review plan (SRP) 3.6.3 Revision 1 for the purpose of eliminating the need to design for dynamic effects that allowed the elimination of pipe whip restraints and jet impingement shields. This SRP was originally written in 1987. The US NRC is currently developing a draft Regulatory Guide on what is called the transition break size (TBS). However, modeling crack pipe response in large complex primary piping systems under seismic loading is a difficult analysis challenge due to many factors. The initial published work (Wilkowski et al., “Robust LBB Analysis for Atucha II Nuclear Plant,†2011 ASME PVP Conference, July 17–21, Baltimore, MD) on the seismic evaluations for the Atucha II plant showed that even with a seismic event with the amplitudes corresponding to the amplitudes for an event with a probability of 1 أ— 10−6 per year, that a doubleended guillotine break (DEGB) was pragmatically impossible due to the high leakage rates and total loss of makeup water inventory. The critical circumferential throughwall flaw size in that case was 94% of the circumference. This paper discusses further efforts to show how much higher the applied accelerations would have to be to cause a DEGB for an initial circumferential throughwall crack that was 33% around the circumference. This flaw length would also be easily detected by leakage and loss of makeup water inventory. These analyses showed that the applied seismic peakground accelerations had to exceed 25 g's for the case of this throughwallcrack to become a DEGB during a single seismic loading event. This is a factor of 80 times higher than the 1 أ— 10−6 seismic event accelerations, or 240 times higher than the safe shutdown earthquake (SSE) accelerations. | |
| publisher | The American Society of Mechanical Engineers (ASME) | |
| title | Leak Before Break Under Beyond Design Basis Seismic Loading | |
| type | Journal Paper | |
| journal volume | 135 | |
| journal issue | 5 | |
| journal title | Journal of Pressure Vessel Technology | |
| identifier doi | 10.1115/1.4024442 | |
| journal fristpage | 51801 | |
| journal lastpage | 51801 | |
| identifier eissn | 1528-8978 | |