YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Optimization of Project Time-Cost Trade-Off Problem with Discounted Cash Flows

    Source: Journal of Construction Engineering and Management:;2011:;Volume ( 137 ):;issue: 001
    Author:
    Mohammad A. Ammar
    DOI: 10.1061/(ASCE)CO.1943-7862.0000256
    Publisher: American Society of Civil Engineers
    Abstract: Traditional time-cost trade-off (TCTO) analysis assumes constant value of activities’ cost along the project time span. However, the value of money decreases with time and, therefore, discounted cash flows should be considered when solving TCTO optimization problem. Optimization problems in project management have been traditionally solved by two distinctive approaches: heuristic methods and optimization techniques. Although heuristic methods can handle large-size projects, they do not guarantee optimal solutions. A nonlinear mathematical optimization model for project TCTO problem is developed, which minimizes project direct cost and takes into account discounted cash flows. Costs of activities are assumed to be incurred at their finish times. The model guarantees the optimal solution, in which precise discrete activity time-cost function is used. The model input includes precedence relationship between project activities, discrete utility data for project activities, and discount rate. Details of model formulation are illustrated by an example project. The results show that selected activities’ durations and costs and consequently optimal project duration differ from traditional analysis if discounted cash flow is considered. The new approach provides project practitioners with a way for considering net present value in time-cost decisions so that the best option can be identified.
    • Download: (1.769Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Optimization of Project Time-Cost Trade-Off Problem with Discounted Cash Flows

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/58408
    Collections
    • Journal of Construction Engineering and Management

    Show full item record

    contributor authorMohammad A. Ammar
    date accessioned2017-05-08T21:39:14Z
    date available2017-05-08T21:39:14Z
    date copyrightJanuary 2011
    date issued2011
    identifier other%28asce%29co%2E1943-7862%2E0000262.pdf
    identifier urihttp://yetl.yabesh.ir/yetl/handle/yetl/58408
    description abstractTraditional time-cost trade-off (TCTO) analysis assumes constant value of activities’ cost along the project time span. However, the value of money decreases with time and, therefore, discounted cash flows should be considered when solving TCTO optimization problem. Optimization problems in project management have been traditionally solved by two distinctive approaches: heuristic methods and optimization techniques. Although heuristic methods can handle large-size projects, they do not guarantee optimal solutions. A nonlinear mathematical optimization model for project TCTO problem is developed, which minimizes project direct cost and takes into account discounted cash flows. Costs of activities are assumed to be incurred at their finish times. The model guarantees the optimal solution, in which precise discrete activity time-cost function is used. The model input includes precedence relationship between project activities, discrete utility data for project activities, and discount rate. Details of model formulation are illustrated by an example project. The results show that selected activities’ durations and costs and consequently optimal project duration differ from traditional analysis if discounted cash flow is considered. The new approach provides project practitioners with a way for considering net present value in time-cost decisions so that the best option can be identified.
    publisherAmerican Society of Civil Engineers
    titleOptimization of Project Time-Cost Trade-Off Problem with Discounted Cash Flows
    typeJournal Paper
    journal volume137
    journal issue1
    journal titleJournal of Construction Engineering and Management
    identifier doi10.1061/(ASCE)CO.1943-7862.0000256
    treeJournal of Construction Engineering and Management:;2011:;Volume ( 137 ):;issue: 001
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian