YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Management in Engineering
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Management in Engineering
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Managing Construction of Israeli Air Bases in Negev—A Personal Perspective

    Source: Journal of Management in Engineering:;1985:;Volume ( 001 ):;issue: 004
    Author:
    John F. Wall, Jr.
    DOI: 10.1061/(ASCE)9742-597X(1985)1:4(233)
    Publisher: American Society of Civil Engineers
    Abstract: In the spring of 1980, the writer became project manager of the Israeli Air Base Program. This called for the U.S. Army Corps of Engineers to build, from scratch, high performance tactical fighter bases at Ramon and Ovda in the Negev Desert to replace two similar bases nearby in the Sinai Peninsula. The project, being carried out in agreement with the Camp David Accord, presented complex and unusual management challenges and brought with it an extraordinary amount of stress and strain. To begin with, Israelis and Americans shared in the management. The U.S. Air Force managed the program, orchestrating and ensuring activation of the two bases. An Israeli program management office also participated. The United States Corps of Engineers was construction agent for the program. Israeli withdrawal from the Sinai depended on the timely completion of the two air bases. The bases themselves were unlike American military airfields, and resembled more land‐based aircraft carriers, with underground hardened hangar complexes connected to multiple runways by high‐speed taxiways. Construction management was not routine. Separate U.S. design‐construct joint ventures carried out the work on each of the two air bases. The contractors, under a cost‐plus‐a‐fixed‐fee contract, were responsible for quality control, while the Corps of Engineers was responsible for quality assurance. Despite management problems, the two bases were built well, completed on time, and within budget.
    • Download: (1.434Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Managing Construction of Israeli Air Bases in Negev—A Personal Perspective

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/55587
    Collections
    • Journal of Management in Engineering

    Show full item record

    contributor authorJohn F. Wall, Jr.
    date accessioned2017-05-08T21:32:42Z
    date available2017-05-08T21:32:42Z
    date copyrightOctober 1985
    date issued1985
    identifier other%28asce%299742-597x%281985%291%3A4%28233%29.pdf
    identifier urihttp://yetl.yabesh.ir/yetl/handle/yetl/55587
    description abstractIn the spring of 1980, the writer became project manager of the Israeli Air Base Program. This called for the U.S. Army Corps of Engineers to build, from scratch, high performance tactical fighter bases at Ramon and Ovda in the Negev Desert to replace two similar bases nearby in the Sinai Peninsula. The project, being carried out in agreement with the Camp David Accord, presented complex and unusual management challenges and brought with it an extraordinary amount of stress and strain. To begin with, Israelis and Americans shared in the management. The U.S. Air Force managed the program, orchestrating and ensuring activation of the two bases. An Israeli program management office also participated. The United States Corps of Engineers was construction agent for the program. Israeli withdrawal from the Sinai depended on the timely completion of the two air bases. The bases themselves were unlike American military airfields, and resembled more land‐based aircraft carriers, with underground hardened hangar complexes connected to multiple runways by high‐speed taxiways. Construction management was not routine. Separate U.S. design‐construct joint ventures carried out the work on each of the two air bases. The contractors, under a cost‐plus‐a‐fixed‐fee contract, were responsible for quality control, while the Corps of Engineers was responsible for quality assurance. Despite management problems, the two bases were built well, completed on time, and within budget.
    publisherAmerican Society of Civil Engineers
    titleManaging Construction of Israeli Air Bases in Negev—A Personal Perspective
    typeJournal Paper
    journal volume1
    journal issue4
    journal titleJournal of Management in Engineering
    identifier doi10.1061/(ASCE)9742-597X(1985)1:4(233)
    treeJournal of Management in Engineering:;1985:;Volume ( 001 ):;issue: 004
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian