YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Prioritizing Construction Activities: Addressing the Flaws of Schedule-Based Indexes

    Source: Journal of Construction Engineering and Management:;2022:;Volume ( 148 ):;issue: 008::page 04022069
    Author:
    Seyed Ashkan Zarghami
    DOI: 10.1061/(ASCE)CO.1943-7862.0002328
    Publisher: ASCE
    Abstract: Research on prioritizing construction activities that are critical to the timely completion of projects rests on a range of indexes that attempt to identify the critical path and capture uncertainty in the duration of project activities. However, these indexes have been shown to have major flaws. These flaws can be classified broadly into two categories: (1) incomplete representation of an activity’s importance; and (2) problems in the mathematical representation of an activity’s importance. This paper developed a new index that addresses the shortcomings of the available schedule-based indexes. The proposed index was applied to a real-life construction project to evaluate the significance of its activities. The results confirmed the substantive influence of the structural organization of the project network on the relative importance of project activities. The key contribution of this research is to offer a richer approach to measuring the importance of construction activities by paying simultaneous attention to uncertainty in completion time, the total float, and the topological characteristics of project activities.
    • Download: (1.244Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Prioritizing Construction Activities: Addressing the Flaws of Schedule-Based Indexes

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/4286136
    Collections
    • Journal of Construction Engineering and Management

    Show full item record

    contributor authorSeyed Ashkan Zarghami
    date accessioned2022-08-18T12:10:28Z
    date available2022-08-18T12:10:28Z
    date issued2022/05/27
    identifier other%28ASCE%29CO.1943-7862.0002328.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4286136
    description abstractResearch on prioritizing construction activities that are critical to the timely completion of projects rests on a range of indexes that attempt to identify the critical path and capture uncertainty in the duration of project activities. However, these indexes have been shown to have major flaws. These flaws can be classified broadly into two categories: (1) incomplete representation of an activity’s importance; and (2) problems in the mathematical representation of an activity’s importance. This paper developed a new index that addresses the shortcomings of the available schedule-based indexes. The proposed index was applied to a real-life construction project to evaluate the significance of its activities. The results confirmed the substantive influence of the structural organization of the project network on the relative importance of project activities. The key contribution of this research is to offer a richer approach to measuring the importance of construction activities by paying simultaneous attention to uncertainty in completion time, the total float, and the topological characteristics of project activities.
    publisherASCE
    titlePrioritizing Construction Activities: Addressing the Flaws of Schedule-Based Indexes
    typeJournal Article
    journal volume148
    journal issue8
    journal titleJournal of Construction Engineering and Management
    identifier doi10.1061/(ASCE)CO.1943-7862.0002328
    journal fristpage04022069
    journal lastpage04022069-12
    page12
    treeJournal of Construction Engineering and Management:;2022:;Volume ( 148 ):;issue: 008
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian