| contributor author | Kyunghwan Kim | |
| contributor author | Jesús M. de la Garza | |
| date accessioned | 2017-05-08T20:41:34Z | |
| date available | 2017-05-08T20:41:34Z | |
| date copyright | March 2005 | |
| date issued | 2005 | |
| identifier other | %28asce%290733-9364%282005%29131%3A3%28330%29.pdf | |
| identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/23698 | |
| description abstract | This paper presents the critical path method forward and backward passes with multiple calendars. Multiple calendars are required in many construction projects to effectively represent various project conditions such as work properties, resource availabilities, weather conditions, etc. For this reason, major project management software packages such as | |
| publisher | American Society of Civil Engineers | |
| title | Critical Path Method with Multiple Calendars | |
| type | Journal Paper | |
| journal volume | 131 | |
| journal issue | 3 | |
| journal title | Journal of Construction Engineering and Management | |
| identifier doi | 10.1061/(ASCE)0733-9364(2005)131:3(330) | |
| tree | Journal of Construction Engineering and Management:;2005:;Volume ( 131 ):;issue: 003 | |
| contenttype | Fulltext | |