Show simple item record

contributor authorKyunghwan Kim
contributor authorJesús M. de la Garza
date accessioned2017-05-08T20:41:34Z
date available2017-05-08T20:41:34Z
date copyrightMarch 2005
date issued2005
identifier other%28asce%290733-9364%282005%29131%3A3%28330%29.pdf
identifier urihttp://yetl.yabesh.ir/yetl/handle/yetl/23698
description abstractThis paper presents the critical path method forward and backward passes with multiple calendars. Multiple calendars are required in many construction projects to effectively represent various project conditions such as work properties, resource availabilities, weather conditions, etc. For this reason, major project management software packages such as
publisherAmerican Society of Civil Engineers
titleCritical Path Method with Multiple Calendars
typeJournal Paper
journal volume131
journal issue3
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/(ASCE)0733-9364(2005)131:3(330)
treeJournal of Construction Engineering and Management:;2005:;Volume ( 131 ):;issue: 003