Framework for Work-Space Planning Using Four-Dimensional BIM in Construction ProjectsSource: Journal of Construction Engineering and Management:;2014:;Volume ( 140 ):;issue: 009DOI: 10.1061/(ASCE)CO.1943-7862.0000885Publisher: American Society of Civil Engineers
Abstract: Each participant in a building construction project requires a dedicated work space in which to execute their activities. In this environment, inappropriate work-space planning in a construction site causes work-space problems, which results in a loss of productivity, safety hazards, and issues of poor quality. Therefore, the work space should be considered one of the most important resources and constraints to manage at a construction site. However, current construction planning techniques have proven to be insufficient for work-space planning because they do not account for the spatial feature of each activity. To establish a formalized work-space planning process, therefore, this paper categorizes work space by its function and movability and suggests a framework for a work-space planning process that contains five phases, including 4D building information model (BIM) generation, work-space requirement identification, work-space occupation representation, work-space problem identification, and work-space problem resolution. The proposed framework in this paper can improve the accuracy of work-space status representation and work-space problem identification by introducing the work-space occupation concept and the integrated work-space planning process that considers characteristics of activity, work space, and construction plan. In addition, this paper aims to ameliorate the work-space planning process through path analysis and a formalized work-space problem resolution process. To validate the proposed approach, a case project was tested. The result shows the efficiency and effectiveness of the proposed framework on improving the work-space planning process. Based on the result of this study, a project manager will be able to prevent possible work-space problems and their negative effects on project performance by devising a pertinent work-space plan during the preconstruction phase.
|
Show full item record
contributor author | Byungjoo Choi | |
contributor author | Hyun-Soo Lee | |
contributor author | Moonseo Park | |
contributor author | Yong K. Cho | |
contributor author | Hyunsoo Kim | |
date accessioned | 2017-05-08T22:06:43Z | |
date available | 2017-05-08T22:06:43Z | |
date copyright | September 2014 | |
date issued | 2014 | |
identifier other | 28718808.pdf | |
identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/71570 | |
description abstract | Each participant in a building construction project requires a dedicated work space in which to execute their activities. In this environment, inappropriate work-space planning in a construction site causes work-space problems, which results in a loss of productivity, safety hazards, and issues of poor quality. Therefore, the work space should be considered one of the most important resources and constraints to manage at a construction site. However, current construction planning techniques have proven to be insufficient for work-space planning because they do not account for the spatial feature of each activity. To establish a formalized work-space planning process, therefore, this paper categorizes work space by its function and movability and suggests a framework for a work-space planning process that contains five phases, including 4D building information model (BIM) generation, work-space requirement identification, work-space occupation representation, work-space problem identification, and work-space problem resolution. The proposed framework in this paper can improve the accuracy of work-space status representation and work-space problem identification by introducing the work-space occupation concept and the integrated work-space planning process that considers characteristics of activity, work space, and construction plan. In addition, this paper aims to ameliorate the work-space planning process through path analysis and a formalized work-space problem resolution process. To validate the proposed approach, a case project was tested. The result shows the efficiency and effectiveness of the proposed framework on improving the work-space planning process. Based on the result of this study, a project manager will be able to prevent possible work-space problems and their negative effects on project performance by devising a pertinent work-space plan during the preconstruction phase. | |
publisher | American Society of Civil Engineers | |
title | Framework for Work-Space Planning Using Four-Dimensional BIM in Construction Projects | |
type | Journal Paper | |
journal volume | 140 | |
journal issue | 9 | |
journal title | Journal of Construction Engineering and Management | |
identifier doi | 10.1061/(ASCE)CO.1943-7862.0000885 | |
tree | Journal of Construction Engineering and Management:;2014:;Volume ( 140 ):;issue: 009 | |
contenttype | Fulltext |