| contributor author | Panagiotis Ch. Anastasopoulos | |
| contributor author | Samuel Labi | |
| contributor author | Abhishek Bhargava | |
| contributor author | Fred L. Mannering | |
| date accessioned | 2017-05-08T21:39:34Z | |
| date available | 2017-05-08T21:39:34Z | |
| date copyright | March 2012 | |
| date issued | 2012 | |
| identifier other | %28asce%29co%2E1943-7862%2E0000443.pdf | |
| identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/58599 | |
| description abstract | Delays in the completion of highway construction and maintenance projects are important concerns to state highway agencies and contractors alike because such time delays can have a number of adverse consequences, such as extending the duration of active work zones, contributing to road-user dissatisfaction and increasing the risk of litigation regarding delay responsibility. In this paper, using data from 1,722 highway projects in Indiana, random-parameter statistical models are estimated to study the factors that contribute to the likelihood of encountering a project time delay and its duration. The model estimation results show that the likelihood and duration of project time delays are significantly influenced by factors such as project cost (contract bid amount), project type, planned project duration, and the likelihood of adverse weather. | |
| publisher | American Society of Civil Engineers | |
| title | Empirical Assessment of the Likelihood and Duration of Highway Project Time Delays | |
| type | Journal Paper | |
| journal volume | 138 | |
| journal issue | 3 | |
| journal title | Journal of Construction Engineering and Management | |
| identifier doi | 10.1061/(ASCE)CO.1943-7862.0000437 | |
| tree | Journal of Construction Engineering and Management:;2012:;Volume ( 138 ):;issue: 003 | |
| contenttype | Fulltext | |