contributor author | Zhen Yu Zhao | |
contributor author | Wei Yang You | |
contributor author | Jian Zuo | |
date accessioned | 2017-05-08T21:39:09Z | |
date available | 2017-05-08T21:39:09Z | |
date copyright | September 2010 | |
date issued | 2010 | |
identifier other | %28asce%29co%2E1943-7862%2E0000216.pdf | |
identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/58361 | |
description abstract | This research proposes an innovative critical chain method (ICCM) for project planning and control under resource constraints and uncertainty. An improved genetic algorithm is developed to identify the critical chain and to obtain the optimal start time of each activity under the most optimistic duration of each activity and resource constraints. Furthermore, a feeding buffer is added in an insert point in order to deal with uncertainties. The benefits of applying this ICCM are demonstrated in an example project. | |
publisher | American Society of Civil Engineers | |
title | Application of Innovative Critical Chain Method for Project Planning and Control under Resource Constraints and Uncertainty | |
type | Journal Paper | |
journal volume | 136 | |
journal issue | 9 | |
journal title | Journal of Construction Engineering and Management | |
identifier doi | 10.1061/(ASCE)CO.1943-7862.0000209 | |
tree | Journal of Construction Engineering and Management:;2010:;Volume ( 136 ):;issue: 009 | |
contenttype | Fulltext | |