YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Management in Engineering
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Management in Engineering
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Determining Delay Accountability, Compensation, and Price Variation Using Computable Smart Contracts in Construction

    Source: Journal of Management in Engineering:;2024:;Volume ( 040 ):;issue: 003::page 04024013-1
    Author:
    Purva Gupta
    ,
    Kumar Neeraj Jha
    DOI: 10.1061/JMENEA.MEENG-5811
    Publisher: ASCE
    Abstract: Several construction projects globally suffer due to time and cost overruns. These could be due to reasons attributable to the contracting parties or unforeseen external circumstances. Disputes often arise between the parties regarding which side caused the delay and the compensation terms for the delay. Thus, this study is motivated to explore a digital contractual solution for contract administrators and project managers using blockchain technology-enabled smart contracts. In this regard, the research attempts to develop smart contract clauses that (1) carefully allocate liability and delay accountability at various construction stages; (2) automatically compute the delay compensations and notify the responsible party; and (3) determine the resultant extensions of time and cost, with cost variations. The goal is to develop computable legal contracts for industry and academia focusing on the extension of time, delay compensation, and variation, which can be applied to all projects worldwide, regardless of the complexity or scale.
    • Download: (6.015Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Price: 5000 Rial
    • Statistics

      Determining Delay Accountability, Compensation, and Price Variation Using Computable Smart Contracts in Construction

    URI
    http://yetl.yabesh.ir/yetl1/handle/yetl/4296583
    Collections
    • Journal of Management in Engineering

    Show full item record

    contributor authorPurva Gupta
    contributor authorKumar Neeraj Jha
    date accessioned2024-04-27T22:24:24Z
    date available2024-04-27T22:24:24Z
    date issued2024/05/01
    identifier other10.1061-JMENEA.MEENG-5811.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4296583
    description abstractSeveral construction projects globally suffer due to time and cost overruns. These could be due to reasons attributable to the contracting parties or unforeseen external circumstances. Disputes often arise between the parties regarding which side caused the delay and the compensation terms for the delay. Thus, this study is motivated to explore a digital contractual solution for contract administrators and project managers using blockchain technology-enabled smart contracts. In this regard, the research attempts to develop smart contract clauses that (1) carefully allocate liability and delay accountability at various construction stages; (2) automatically compute the delay compensations and notify the responsible party; and (3) determine the resultant extensions of time and cost, with cost variations. The goal is to develop computable legal contracts for industry and academia focusing on the extension of time, delay compensation, and variation, which can be applied to all projects worldwide, regardless of the complexity or scale.
    publisherASCE
    titleDetermining Delay Accountability, Compensation, and Price Variation Using Computable Smart Contracts in Construction
    typeJournal Article
    journal volume40
    journal issue3
    journal titleJournal of Management in Engineering
    identifier doi10.1061/JMENEA.MEENG-5811
    journal fristpage04024013-1
    journal lastpage04024013-17
    page17
    treeJournal of Management in Engineering:;2024:;Volume ( 040 ):;issue: 003
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian