YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Robustness Analysis of Total Project Cost and Schedule Delay and Overrun Indicators of Heavy Industrial Projects

    Source: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2023:;Volume ( 015 ):;issue: 002::page 04523005-1
    Author:
    Sharareh Kermanshachi
    ,
    Apurva Pamidimukkala
    DOI: 10.1061/JLADAH.LADR-942
    Publisher: American Society of Civil Engineers
    Abstract: Barriers such as cost overruns and schedule delays make it challenging to achieve successful project outcomes. Their early detection, however, allows mitigation strategies to be implemented before too much delay has occurred; therefore, the objective of this study was to identify the total project cost and schedule overrun indicators and evaluate their reliability for large-scale heavy industrial projects. To accomplish the study’s goals, a structured survey was developed and disseminated to construction industry professionals to gain their input on the most important cost overrun indicators (COIs) and schedule overrun indicators (SOIs). The collected data were analyzed by applying various statistical tests, and a list of the significant COIs and SOIs was compiled utilizing all-possible regression. The extreme bound analysis (EBA) method was adopted to determine the robustness of the identified indicators. The results revealed the nine COIs are design phase contract type, change management approach, degree of internal stakeholders’ alignment, delay in the delivery of long-term facility machinery, proportion of artisanal labor sourced locally, proportion of design completion before the budget approval of the project, preparing for startup deployment, agreement including delayed completion charges, and number of design organizations; two of these were fragile indicators. The results also demonstrated the nine influential indicators for total schedule overrun are implementation of front-end planning, efficacy of the change management process, project population density, average number of project management (PM) team participants in the procurement phase, prior designer and contractor partnership, delay in the delivery of long-term facility machinery, average size of PM team design phase, efficacy of designers group interaction, and number of subcontracting firms; six of these were robustly related to the model. The findings of this study can help construction project decision makers focus on the most reliable indicators and reduce the number of revisions required throughout the execution of a project.
    • Download: (1.955Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Price: 5000 Rial
    • Statistics

      Robustness Analysis of Total Project Cost and Schedule Delay and Overrun Indicators of Heavy Industrial Projects

    URI
    http://yetl.yabesh.ir/yetl1/handle/yetl/4292887
    Collections
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction

    Show full item record

    contributor authorSharareh Kermanshachi
    contributor authorApurva Pamidimukkala
    date accessioned2023-08-16T19:10:50Z
    date available2023-08-16T19:10:50Z
    date issued2023/05/01
    identifier otherJLADAH.LADR-942.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4292887
    description abstractBarriers such as cost overruns and schedule delays make it challenging to achieve successful project outcomes. Their early detection, however, allows mitigation strategies to be implemented before too much delay has occurred; therefore, the objective of this study was to identify the total project cost and schedule overrun indicators and evaluate their reliability for large-scale heavy industrial projects. To accomplish the study’s goals, a structured survey was developed and disseminated to construction industry professionals to gain their input on the most important cost overrun indicators (COIs) and schedule overrun indicators (SOIs). The collected data were analyzed by applying various statistical tests, and a list of the significant COIs and SOIs was compiled utilizing all-possible regression. The extreme bound analysis (EBA) method was adopted to determine the robustness of the identified indicators. The results revealed the nine COIs are design phase contract type, change management approach, degree of internal stakeholders’ alignment, delay in the delivery of long-term facility machinery, proportion of artisanal labor sourced locally, proportion of design completion before the budget approval of the project, preparing for startup deployment, agreement including delayed completion charges, and number of design organizations; two of these were fragile indicators. The results also demonstrated the nine influential indicators for total schedule overrun are implementation of front-end planning, efficacy of the change management process, project population density, average number of project management (PM) team participants in the procurement phase, prior designer and contractor partnership, delay in the delivery of long-term facility machinery, average size of PM team design phase, efficacy of designers group interaction, and number of subcontracting firms; six of these were robustly related to the model. The findings of this study can help construction project decision makers focus on the most reliable indicators and reduce the number of revisions required throughout the execution of a project.
    publisherAmerican Society of Civil Engineers
    titleRobustness Analysis of Total Project Cost and Schedule Delay and Overrun Indicators of Heavy Industrial Projects
    typeJournal Article
    journal volume15
    journal issue2
    journal titleJournal of Legal Affairs and Dispute Resolution in Engineering and Construction
    identifier doi10.1061/JLADAH.LADR-942
    journal fristpage04523005-1
    journal lastpage04523005-10
    page10
    treeJournal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2023:;Volume ( 015 ):;issue: 002
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian