YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Work Density Method for Takt Planning of Construction Processes with Nonrepetitive Work

    Source: Journal of Construction Engineering and Management:;2022:;Volume ( 148 ):;issue: 012::page 04022134
    Author:
    Iris D. Tommelein
    DOI: 10.1061/(ASCE)CO.1943-7862.0002398
    Publisher: ASCE
    Abstract: A new method is presented for construction process planning. It is based on the concept of work density and called the Work Density Method (WDM), two terms coined for use in this context. Using the WDM, planners create one-piece workflow by dividing work space into zones while assigning each zone exclusively for each trade to complete their work, with trades working in consecutive process steps, each one taking up to the same fixed amount of time. The method supports development of a plan (using takt or not) for repetitive as well as nonrepetitive work thanks to work density serving as the common unit to describe workload. The WDM is an iterative method using work structuring to decide a sequence of process steps, zone the work space while lowering the peak of the cumulative work density (i.e., workload peak), determine a lower bound on the takt that can be met, and verify this meets customer requirements. The method was developed experimentally on a live project. This paper rationalizes the use of work density in planning, illustrates the WDM using examples, presents a paradox, and suggests method enhancements. The contribution to knowledge is the formulation of a new planning method that augments existing planning methods. On construction projects where speed is of the essence, activities must get scheduled in parallel and take place in multiple locations simultaneously. Those locations must be clearly demarcated in order to avoid the detrimental impact of trade stacking, and activity completion times must be strictly adhered to in order to avoid cascading delays. The WDM presented in this paper offers a systematic approach to determine such locations and to set a time limit within which activities must be completed. This new method is intended for use by superintendents together with their trade partners to develop an execution strategy so that they will be able to reliably hit milestones shown on their project master schedule. Some planners may already be familiar with the notion of work density and be using it intuitively when considering options to shorten a project’s duration. In this paper, a new, formal method is presented. It is illustrated by various examples. The use of computational support tools is suggested for practical implementation.
    • Download: (2.406Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Price: 5000 Rial
    • Statistics

      Work Density Method for Takt Planning of Construction Processes with Nonrepetitive Work

    URI
    http://yetl.yabesh.ir/yetl1/handle/yetl/4289547
    Collections
    • Journal of Construction Engineering and Management

    Show full item record

    contributor authorIris D. Tommelein
    date accessioned2023-04-07T00:41:18Z
    date available2023-04-07T00:41:18Z
    date issued2022/12/01
    identifier other%28ASCE%29CO.1943-7862.0002398.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4289547
    description abstractA new method is presented for construction process planning. It is based on the concept of work density and called the Work Density Method (WDM), two terms coined for use in this context. Using the WDM, planners create one-piece workflow by dividing work space into zones while assigning each zone exclusively for each trade to complete their work, with trades working in consecutive process steps, each one taking up to the same fixed amount of time. The method supports development of a plan (using takt or not) for repetitive as well as nonrepetitive work thanks to work density serving as the common unit to describe workload. The WDM is an iterative method using work structuring to decide a sequence of process steps, zone the work space while lowering the peak of the cumulative work density (i.e., workload peak), determine a lower bound on the takt that can be met, and verify this meets customer requirements. The method was developed experimentally on a live project. This paper rationalizes the use of work density in planning, illustrates the WDM using examples, presents a paradox, and suggests method enhancements. The contribution to knowledge is the formulation of a new planning method that augments existing planning methods. On construction projects where speed is of the essence, activities must get scheduled in parallel and take place in multiple locations simultaneously. Those locations must be clearly demarcated in order to avoid the detrimental impact of trade stacking, and activity completion times must be strictly adhered to in order to avoid cascading delays. The WDM presented in this paper offers a systematic approach to determine such locations and to set a time limit within which activities must be completed. This new method is intended for use by superintendents together with their trade partners to develop an execution strategy so that they will be able to reliably hit milestones shown on their project master schedule. Some planners may already be familiar with the notion of work density and be using it intuitively when considering options to shorten a project’s duration. In this paper, a new, formal method is presented. It is illustrated by various examples. The use of computational support tools is suggested for practical implementation.
    publisherASCE
    titleWork Density Method for Takt Planning of Construction Processes with Nonrepetitive Work
    typeJournal Article
    journal volume148
    journal issue12
    journal titleJournal of Construction Engineering and Management
    identifier doi10.1061/(ASCE)CO.1943-7862.0002398
    journal fristpage04022134
    journal lastpage04022134_14
    page14
    treeJournal of Construction Engineering and Management:;2022:;Volume ( 148 ):;issue: 012
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian