Administering Change Orders in Highway ProjectsSource: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2021:;Volume ( 014 ):;issue: 002::page 05021010Author:Muaz O. Ahmed
,
Rayan H. Assaad
,
Islam H. El-adaway
,
Emily Echele
,
Kyle Govro
,
John Watson
DOI: 10.1061/(ASCE)LA.1943-4170.0000528Publisher: ASCE
Abstract: Change orders continue to be one of the main challenges faced by the construction industry. Despite many previous research efforts related to managing change orders in the construction industry, there is still a lack of research that investigates the contractual aspects of change orders for transportation projects. This paper tackles this knowledge gap within the context of Ohio Department of Transportation (ODOT) highway projects. To this end, the authors used an integrated research method comprised of (1) selection and analysis of ODOT case studies; (2) identification of the main change orders aspects that lead to conflicts, claims, and/or disputes in the considered case studies; and (3) analysis of the contractual provisions and procedures related to change orders on ODOT projects. The authors consulted throughout all the research steps with ODOT experts for verification and validation. Through the analysis of 10 ODOT case studies, results show that the major contractual challenges related to change orders on ODOT projects are caused by definition terms and their associated processes, approvals according to the contractual provisions, and approvals in light of the applicable laws. Accordingly, this paper identifies (1) a list of opportunities and risks, and (2) a series of checklist questions. These research outcomes shall help project parties in identifying the contract terms that can lead to improper handling of change orders, and thus facilitate better managing of change orders on ODOT projects. Ultimately, this research adds to the body of knowledge by providing contractual guidelines to facilitate a better administration of the contractual procedures of change orders for a timely and cost-effective execution of highway transportation projects.
|
Show full item record
| contributor author | Muaz O. Ahmed | |
| contributor author | Rayan H. Assaad | |
| contributor author | Islam H. El-adaway | |
| contributor author | Emily Echele | |
| contributor author | Kyle Govro | |
| contributor author | John Watson | |
| date accessioned | 2022-05-07T19:52:59Z | |
| date available | 2022-05-07T19:52:59Z | |
| date issued | 2021-12-28 | |
| identifier other | (ASCE)LA.1943-4170.0000528.pdf | |
| identifier uri | http://yetl.yabesh.ir/yetl1/handle/yetl/4281773 | |
| description abstract | Change orders continue to be one of the main challenges faced by the construction industry. Despite many previous research efforts related to managing change orders in the construction industry, there is still a lack of research that investigates the contractual aspects of change orders for transportation projects. This paper tackles this knowledge gap within the context of Ohio Department of Transportation (ODOT) highway projects. To this end, the authors used an integrated research method comprised of (1) selection and analysis of ODOT case studies; (2) identification of the main change orders aspects that lead to conflicts, claims, and/or disputes in the considered case studies; and (3) analysis of the contractual provisions and procedures related to change orders on ODOT projects. The authors consulted throughout all the research steps with ODOT experts for verification and validation. Through the analysis of 10 ODOT case studies, results show that the major contractual challenges related to change orders on ODOT projects are caused by definition terms and their associated processes, approvals according to the contractual provisions, and approvals in light of the applicable laws. Accordingly, this paper identifies (1) a list of opportunities and risks, and (2) a series of checklist questions. These research outcomes shall help project parties in identifying the contract terms that can lead to improper handling of change orders, and thus facilitate better managing of change orders on ODOT projects. Ultimately, this research adds to the body of knowledge by providing contractual guidelines to facilitate a better administration of the contractual procedures of change orders for a timely and cost-effective execution of highway transportation projects. | |
| publisher | ASCE | |
| title | Administering Change Orders in Highway Projects | |
| type | Journal Paper | |
| journal volume | 14 | |
| journal issue | 2 | |
| journal title | Journal of Legal Affairs and Dispute Resolution in Engineering and Construction | |
| identifier doi | 10.1061/(ASCE)LA.1943-4170.0000528 | |
| journal fristpage | 05021010 | |
| journal lastpage | 05021010-18 | |
| page | 18 | |
| tree | Journal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2021:;Volume ( 014 ):;issue: 002 | |
| contenttype | Fulltext |