YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Leveraging the Value of Project Scope Growth through Construction Manager-at-Risk Delivery of Public University Capital Improvement Projects

    Source: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2021:;Volume ( 014 ):;issue: 001::page 04521042
    Author:
    Nils J. Gransberg
    ,
    Safa Maraqa
    DOI: 10.1061/(ASCE)LA.1943-4170.0000514
    Publisher: ASCE
    Abstract: When capital improvement project final costs exceed initial estimates, the overrun is assumed to be an indication of poor performance. However, when a project owner adds scope at any point after the initial estimate, the value of the project is enhanced, even though the numbers are interpreted in a negative light. This paper explores the idea that construction manager-at-risk (CMR) delivery provides a level of contractual flexibility that is not available in traditional design-bid-build (DBB) contracts and, consequently, lends itself to projects in which additional funding may become available after contract award and facilitates the efficient use of such funds in a manner not available in DBB-delivered projects. This study reviewed the cost performance of 166 CMR and DBB projects completed by 23 American public universities valued at over $3 billion from 2018 to 2019. The study found that cost growth in university CMR projects was greater than in similar DBB projects, contradicting the conclusions of most of the literature on CMR. The analysis of a second sample of 86 projects, which individually compared DBB projects with similar CMR projects, found that CMR project design fee efficiency was double that of DBB. The first contribution of this study is the provision of an objective metric for differentiating between owner-driven scope cost growth and cost growth due to other reasons; the second contribution is the finding that the contractual flexibility inherent to CMR project delivery adds value for money by allowing a university to expeditiously obligate new sources of funding, such as donations.
    • Download: (220.2Kb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Price: 5000 Rial
    • Statistics

      Leveraging the Value of Project Scope Growth through Construction Manager-at-Risk Delivery of Public University Capital Improvement Projects

    URI
    http://yetl.yabesh.ir/yetl1/handle/yetl/4281759
    Collections
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction

    Show full item record

    contributor authorNils J. Gransberg
    contributor authorSafa Maraqa
    date accessioned2022-05-07T19:52:04Z
    date available2022-05-07T19:52:04Z
    date issued2021-11-11
    identifier other(ASCE)LA.1943-4170.0000514.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4281759
    description abstractWhen capital improvement project final costs exceed initial estimates, the overrun is assumed to be an indication of poor performance. However, when a project owner adds scope at any point after the initial estimate, the value of the project is enhanced, even though the numbers are interpreted in a negative light. This paper explores the idea that construction manager-at-risk (CMR) delivery provides a level of contractual flexibility that is not available in traditional design-bid-build (DBB) contracts and, consequently, lends itself to projects in which additional funding may become available after contract award and facilitates the efficient use of such funds in a manner not available in DBB-delivered projects. This study reviewed the cost performance of 166 CMR and DBB projects completed by 23 American public universities valued at over $3 billion from 2018 to 2019. The study found that cost growth in university CMR projects was greater than in similar DBB projects, contradicting the conclusions of most of the literature on CMR. The analysis of a second sample of 86 projects, which individually compared DBB projects with similar CMR projects, found that CMR project design fee efficiency was double that of DBB. The first contribution of this study is the provision of an objective metric for differentiating between owner-driven scope cost growth and cost growth due to other reasons; the second contribution is the finding that the contractual flexibility inherent to CMR project delivery adds value for money by allowing a university to expeditiously obligate new sources of funding, such as donations.
    publisherASCE
    titleLeveraging the Value of Project Scope Growth through Construction Manager-at-Risk Delivery of Public University Capital Improvement Projects
    typeJournal Paper
    journal volume14
    journal issue1
    journal titleJournal of Legal Affairs and Dispute Resolution in Engineering and Construction
    identifier doi10.1061/(ASCE)LA.1943-4170.0000514
    journal fristpage04521042
    journal lastpage04521042-12
    page12
    treeJournal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2021:;Volume ( 014 ):;issue: 001
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian