YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Visual and Virtual Production Management System for Proactive Project Controls

    Source: Journal of Construction Engineering and Management:;2021:;Volume ( 147 ):;issue: 007::page 04021058-1
    Author:
    Jacob J. Lin
    ,
    Mani Golparvar-Fard
    DOI: 10.1061/(ASCE)CO.1943-7862.0002045
    Publisher: ASCE
    Abstract: Current construction still suffers from significant schedule delays and budget overruns due to inefficient and retroactive project controls programs. This paper developed a visual and virtual project control system that proactively promotes team-based planning and real-time communication of progress and schedule risk. The system benefits from the growth of visual data on construction sites and the increasing maturity level of building information modeling (BIM), to map the current state of production in 3D and expose waste. By modeling production trends, reliability in the future state of production is forecasted to highlight potential delay issues in a location-driven scheme. A visual 3D interface supports collaborative decision-making to eliminate root causes of waste, enables pull flows between people and information, decentralizes work tracking, and facilitates in-process quality control and hand-overs among contractors. This system was implemented on two projects to validate the underlying algorithms. Results show that the system’s functional aspects improve transparency, accountability, and traceability in project execution, and streamline communications between the field and the office. Specifically, 30% PPC increase and four weeks project completion date advance have been observed. Limitations such as resistance to workflow changes could be further improved in the future through early system introduction.
    • Download: (4.683Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Price: 5000 Rial
    • Statistics

      Visual and Virtual Production Management System for Proactive Project Controls

    URI
    http://yetl.yabesh.ir/yetl1/handle/yetl/4271020
    Collections
    • Journal of Construction Engineering and Management

    Show full item record

    contributor authorJacob J. Lin
    contributor authorMani Golparvar-Fard
    date accessioned2022-02-01T00:10:11Z
    date available2022-02-01T00:10:11Z
    date issued7/1/2021
    identifier other%28ASCE%29CO.1943-7862.0002045.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4271020
    description abstractCurrent construction still suffers from significant schedule delays and budget overruns due to inefficient and retroactive project controls programs. This paper developed a visual and virtual project control system that proactively promotes team-based planning and real-time communication of progress and schedule risk. The system benefits from the growth of visual data on construction sites and the increasing maturity level of building information modeling (BIM), to map the current state of production in 3D and expose waste. By modeling production trends, reliability in the future state of production is forecasted to highlight potential delay issues in a location-driven scheme. A visual 3D interface supports collaborative decision-making to eliminate root causes of waste, enables pull flows between people and information, decentralizes work tracking, and facilitates in-process quality control and hand-overs among contractors. This system was implemented on two projects to validate the underlying algorithms. Results show that the system’s functional aspects improve transparency, accountability, and traceability in project execution, and streamline communications between the field and the office. Specifically, 30% PPC increase and four weeks project completion date advance have been observed. Limitations such as resistance to workflow changes could be further improved in the future through early system introduction.
    publisherASCE
    titleVisual and Virtual Production Management System for Proactive Project Controls
    typeJournal Paper
    journal volume147
    journal issue7
    journal titleJournal of Construction Engineering and Management
    identifier doi10.1061/(ASCE)CO.1943-7862.0002045
    journal fristpage04021058-1
    journal lastpage04021058-17
    page17
    treeJournal of Construction Engineering and Management:;2021:;Volume ( 147 ):;issue: 007
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian