Grouting Methods in Manhole Rehabilitations at Coastal Areas: Case StudySource: Journal of Pipeline Systems Engineering and Practice:;2021:;Volume ( 012 ):;issue: 003::page 05021003-1DOI: 10.1061/(ASCE)PS.1949-1204.0000542Publisher: ASCE
Abstract: For underground structures at coastal areas, inflow/infiltration (I/I) control is a critical procedure to guarantee their quality, especially for manholes, which are more likely to have structural problems and I/I problems. There are several methods that could address these problems, including spraying, grouting, and in situ lining. In this case study, a combined grouting method is proposed for a deep-buried double-walled manhole rehabilitation project, the Diyar Al Muharraq (DAM) project in Bahrain. This case study involves I/I investigation, rehabilitation design, construction management, and evaluation of rehabilitation according to the monitoring data. The 4-step grouting method shows an excellent rehabilitation performance, the monitoring data show that the water level in manholes lowered by 21.35%, and the brine pressure at the bottom of manholes decreased by 78.26%, which means the combined grouting method is effective for manhole rehabilitation at coastal areas.
|
Show full item record
| contributor author | Zihao Zhu | |
| contributor author | Baosong Ma | |
| contributor author | Wenfang Wu | |
| contributor author | Yahong Zhao | |
| contributor author | Tie Wang | |
| contributor author | Cong Zeng | |
| date accessioned | 2022-01-31T23:42:24Z | |
| date available | 2022-01-31T23:42:24Z | |
| date issued | 8/1/2021 | |
| identifier other | %28ASCE%29PS.1949-1204.0000542.pdf | |
| identifier uri | http://yetl.yabesh.ir/yetl1/handle/yetl/4270206 | |
| description abstract | For underground structures at coastal areas, inflow/infiltration (I/I) control is a critical procedure to guarantee their quality, especially for manholes, which are more likely to have structural problems and I/I problems. There are several methods that could address these problems, including spraying, grouting, and in situ lining. In this case study, a combined grouting method is proposed for a deep-buried double-walled manhole rehabilitation project, the Diyar Al Muharraq (DAM) project in Bahrain. This case study involves I/I investigation, rehabilitation design, construction management, and evaluation of rehabilitation according to the monitoring data. The 4-step grouting method shows an excellent rehabilitation performance, the monitoring data show that the water level in manholes lowered by 21.35%, and the brine pressure at the bottom of manholes decreased by 78.26%, which means the combined grouting method is effective for manhole rehabilitation at coastal areas. | |
| publisher | ASCE | |
| title | Grouting Methods in Manhole Rehabilitations at Coastal Areas: Case Study | |
| type | Journal Paper | |
| journal volume | 12 | |
| journal issue | 3 | |
| journal title | Journal of Pipeline Systems Engineering and Practice | |
| identifier doi | 10.1061/(ASCE)PS.1949-1204.0000542 | |
| journal fristpage | 05021003-1 | |
| journal lastpage | 05021003-12 | |
| page | 12 | |
| tree | Journal of Pipeline Systems Engineering and Practice:;2021:;Volume ( 012 ):;issue: 003 | |
| contenttype | Fulltext |