contributor author | Junghye Son; Nabeel Khwaja; Duane S. Milligan | |
date accessioned | 2019-03-10T12:02:03Z | |
date available | 2019-03-10T12:02:03Z | |
date issued | 2019 | |
identifier other | %28ASCE%29CO.1943-7862.0001637.pdf | |
identifier uri | http://yetl.yabesh.ir/yetl1/handle/yetl/4254702 | |
description abstract | Estimation of highway project construction time prior to design development has received comparatively little focus from researchers. State transportation agencies (STAs) and their management teams need a method or tool to estimate construction time during the project planning and development phases, where STAs typically manage hundreds of projects at the program level. These programs of projects are updated periodically, which requires an estimation methodology that is efficient, less time consuming, and reliable during the phases where limited project information is available. This paper presents an approach to developing a planning-phase construction time estimation model using linear regression modeling on actual construction time and cost data from 623 highway projects completed by the Dallas District Office, Texas Department of Transportation (TxDOT). The study developed a multiple linear regression model with three project parameters that were identified as key predictors to construction time. The accuracy and reliability of the developed model were higher than those of the well-known Bromilow’s time-cost (BTC) model. The model was also validated by the Mann-Whitney test of its applicability to a large group of projects. The proposed model requires less effort to develop, update, and revise with new data, which allows STAs to conduct planning-phase estimation of the construction time of a large portfolio of diverse projects effectively and efficiently. STAs would benefit from using this model in various project planning areas such as financial planning, staff planning, transportation impact mitigation, budget allocation, and project prioritization. This study also contributes to the body of knowledge with the proposed construction time estimation methodology during the planning and development phase that has been less focused. | |
publisher | American Society of Civil Engineers | |
title | Planning-Phase Estimation of Construction Time for a Large Portfolio of Highway Projects | |
type | Journal Paper | |
journal volume | 145 | |
journal issue | 4 | |
journal title | Journal of Construction Engineering and Management | |
identifier doi | 10.1061/(ASCE)CO.1943-7862.0001637 | |
page | 04019018 | |
tree | Journal of Construction Engineering and Management:;2019:;Volume ( 145 ):;issue: 004 | |
contenttype | Fulltext | |