description abstractThe critical path method has been increasingly used as an administrative and legal tool rather than as a planning instrument. The writer claims that this evolution has made its planning function of little use to the contractor, using the contract clause of the Federal Government regarding the method of determining allowable contract delay as an illustration. It is asserted that this clause greatly increases the contractors' responsibilities for planning, at the expense of efficient construction management.
publisherAmerican Society of Civil Engineers
titleThe Federal Government and the Critical Path
typeJournal Paper
journal volume112
journal issue2
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/(ASCE)0733-9364(1986)112:2(220)
treeJournal of Construction Engineering and Management:;1986:;Volume ( 112 ):;issue: 002