contributor author | Peter E. D. Love | |
contributor author | Raymond Y. C. Tse | |
contributor author | David J. Edwards | |
date accessioned | 2017-05-08T20:41:11Z | |
date available | 2017-05-08T20:41:11Z | |
date copyright | February 2005 | |
date issued | 2005 | |
identifier other | %28asce%290733-9364%282005%29131%3A2%28187%29.pdf | |
identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/23497 | |
description abstract | Project time–cost relationships were examined by using project scope factors as predictors for 161 construction projects that were completed in various Australian States using the multiple regression technique of weighted least squares. The analysis was performed between project duration (i.e., time), project type, procurement method, tender type, gross floor area (GFA), and number of stories. An alternative model to that proposed by Bromilow more than three decades ago for forecasting time and cost performance is proposed. It is shown that GFA and the number of stories in a building are key determinants of time performance in projects. Furthermore, the results indicate that cost is a poor predictor of time performance. Limitations and practical implications of the research are also presented. | |
publisher | American Society of Civil Engineers | |
title | Time–Cost Relationships in Australian Building Construction Projects | |
type | Journal Paper | |
journal volume | 131 | |
journal issue | 2 | |
journal title | Journal of Construction Engineering and Management | |
identifier doi | 10.1061/(ASCE)0733-9364(2005)131:2(187) | |
tree | Journal of Construction Engineering and Management:;2005:;Volume ( 131 ):;issue: 002 | |
contenttype | Fulltext | |