| contributor author | Y. Rosenfeld | |
| contributor author | R. Navon | |
| contributor author | L. Cohen | |
| date accessioned | 2017-05-08T22:38:54Z | |
| date available | 2017-05-08T22:38:54Z | |
| date copyright | May 1998 | |
| date issued | 1998 | |
| identifier other | %28asce%290733-9364%281998%29124%3A3%28176%29.pdf | |
| identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/84979 | |
| description abstract | This paper presents a study carried out by Technion and the construction department of the Israeli air force, with the objective of identifying opportunities for shortening the duration of construction projects by the adoption of innovative construction technologies in selected areas. This study focused on technological aspects and did not deal with the examination of management practices or organizational issues. Promising candidates for technological improvement were identified and prioritized by means of a comprehensive in-depth survey conducted among the organization's most experienced experts. The survey was aimed at the use of multidimensional Pareto analysis, which distinctly identified (1) the technological resources, (b) the types of projects, and (c) the types of activities that would make the most effective impact. The partial results were intersected mutually to single out the most potent combinations. This paper describes both the method and the results of the analysis. | |
| publisher | American Society of Civil Engineers | |
| title | Methodology for Prioritizing Cost-Effective Construction Technologies | |
| type | Journal Paper | |
| journal volume | 124 | |
| journal issue | 3 | |
| journal title | Journal of Construction Engineering and Management | |
| identifier doi | 10.1061/(ASCE)0733-9364(1998)124:3(176) | |
| tree | Journal of Construction Engineering and Management:;1998:;Volume ( 124 ):;issue: 003 | |
| contenttype | Fulltext | |