| contributor author | A. J. Powderham | |
| contributor author | G. J. Tamaro | |
| date accessioned | 2017-05-08T22:28:48Z | |
| date available | 2017-05-08T22:28:48Z | |
| date copyright | September 1995 | |
| date issued | 1995 | |
| identifier other | %28asce%290733-9364%281995%29121%3A3%28266%29.pdf | |
| identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/81286 | |
| description abstract | Settlements occurring during the first phase of tunneling for the extension of the Docklands Light Railway in London caused concern for damage to the Mansion House during subsequent phases of the work. The building is a landmark structure and no further damage could be accepted. Tunneling was halted until a satisfactory protection program was in place. Various means of protecting the structure were investigated, ranging from full structural underpinning to a least-risk methodology based on the observational method. This paper describes the background to the development and implementation of the observational method to successfully protect the building and complete construction. This required appropriate contingency measures to be identified and planned in advance. Of the contingencies involving preventive or strengthening works, a system of structural ties through the building was selected as most appropriate, least risky, and most economical. Trigger levels for building response were established. Extensive instrumentation was installed and the building was fully monitored during the subsequent phases of tunneling. | |
| publisher | American Society of Civil Engineers | |
| title | Mansion House London: Risk Assessment and Protection | |
| type | Journal Paper | |
| journal volume | 121 | |
| journal issue | 3 | |
| journal title | Journal of Construction Engineering and Management | |
| identifier doi | 10.1061/(ASCE)0733-9364(1995)121:3(266) | |
| tree | Journal of Construction Engineering and Management:;1995:;Volume ( 121 ):;issue: 003 | |
| contenttype | Fulltext | |