YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Critical Analysis of Time and Cost of Management and Traditional Contracts

    Source: Journal of Construction Engineering and Management:;1994:;Volume ( 120 ):;issue: 004
    Author:
    Shamil G. Naoum
    DOI: 10.1061/(ASCE)0733-9364(1994)120:4(687)
    Publisher: American Society of Civil Engineers
    Abstract: This paper presents some findings of a PhD research program conducted by Naoum in 1989, which sought to investigate whether the means of procurement influenced project performance. Ten factors were identified to measure project performance: (1) Preconstruction time; (2) construction time; (3) total time; (4) speed of construction; (5) unit cost of building; (6) time overrun; (7) cost overrun; and client satisfaction with (8) time, (9) cost, and (10) quality. A theoretical framework was used to assist in comparing project performance in a case study sample of 39 management contracts and 30 traditional contracts. From the evidence available in the writer's study, it must be concluded that in neither the management nor the traditional system lies the solution to all the problems facing the construction industry. To achieve project success, the parties need to match the various organizational forms to the client's characteristics, criteria, and priorities with respect to time, cost, and quality. The statistical analysis suggests that management contracting performs significantly better in some respects than traditional contracting, in particular, when time was the essence of the contract and when the project was highly complex. However, the research did not provide enough evidence to support the view that management contracting can reduce the overall building cost, or that the system can increase the standard of quality.
    • Download: (1.066Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Critical Analysis of Time and Cost of Management and Traditional Contracts

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/75842
    Collections
    • Journal of Construction Engineering and Management

    Show full item record

    contributor authorShamil G. Naoum
    date accessioned2017-05-08T22:16:27Z
    date available2017-05-08T22:16:27Z
    date copyrightDecember 1994
    date issued1994
    identifier other%28asce%290733-9364%281994%29120%3A4%28687%29.pdf
    identifier urihttp://yetl.yabesh.ir/yetl/handle/yetl/75842
    description abstractThis paper presents some findings of a PhD research program conducted by Naoum in 1989, which sought to investigate whether the means of procurement influenced project performance. Ten factors were identified to measure project performance: (1) Preconstruction time; (2) construction time; (3) total time; (4) speed of construction; (5) unit cost of building; (6) time overrun; (7) cost overrun; and client satisfaction with (8) time, (9) cost, and (10) quality. A theoretical framework was used to assist in comparing project performance in a case study sample of 39 management contracts and 30 traditional contracts. From the evidence available in the writer's study, it must be concluded that in neither the management nor the traditional system lies the solution to all the problems facing the construction industry. To achieve project success, the parties need to match the various organizational forms to the client's characteristics, criteria, and priorities with respect to time, cost, and quality. The statistical analysis suggests that management contracting performs significantly better in some respects than traditional contracting, in particular, when time was the essence of the contract and when the project was highly complex. However, the research did not provide enough evidence to support the view that management contracting can reduce the overall building cost, or that the system can increase the standard of quality.
    publisherAmerican Society of Civil Engineers
    titleCritical Analysis of Time and Cost of Management and Traditional Contracts
    typeJournal Paper
    journal volume120
    journal issue4
    journal titleJournal of Construction Engineering and Management
    identifier doi10.1061/(ASCE)0733-9364(1994)120:4(687)
    treeJournal of Construction Engineering and Management:;1994:;Volume ( 120 ):;issue: 004
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian