YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Temporary Heating in Construction Contracts

    Source: Journal of Construction Engineering and Management:;1983:;Volume ( 109 ):;issue: 004
    Author:
    Haim Schlick
    DOI: 10.1061/(ASCE)0733-9364(1983)109:4(447)
    Publisher: American Society of Civil Engineers
    Abstract: It appears that in construction projects extending through winter with freezing temperatures, the cost of temporary heating is not always equitably resolved between the parties in a contract. Although existing guidelines have been initiated since 1964 by the construction industry, the bid allowances in calendar days and cost perdiem of heating, as suggested, have not been implemented. The three case studies described with varying structures and heating systems, show how heating costs are affected by changes beyond the General Contractor's control. These costs can be substantial; however, they can be minimized if owner, designer, contractor and mechanical subcontractor can cooperate.
    • Download: (841.1Kb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Temporary Heating in Construction Contracts

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/55730
    Collections
    • Journal of Construction Engineering and Management

    Show full item record

    contributor authorHaim Schlick
    date accessioned2017-05-08T21:32:56Z
    date available2017-05-08T21:32:56Z
    date copyrightDecember 1983
    date issued1983
    identifier other%28asce%290733-9364%281983%29109%3A4%28447%29.pdf
    identifier urihttp://yetl.yabesh.ir/yetl/handle/yetl/55730
    description abstractIt appears that in construction projects extending through winter with freezing temperatures, the cost of temporary heating is not always equitably resolved between the parties in a contract. Although existing guidelines have been initiated since 1964 by the construction industry, the bid allowances in calendar days and cost perdiem of heating, as suggested, have not been implemented. The three case studies described with varying structures and heating systems, show how heating costs are affected by changes beyond the General Contractor's control. These costs can be substantial; however, they can be minimized if owner, designer, contractor and mechanical subcontractor can cooperate.
    publisherAmerican Society of Civil Engineers
    titleTemporary Heating in Construction Contracts
    typeJournal Paper
    journal volume109
    journal issue4
    journal titleJournal of Construction Engineering and Management
    identifier doi10.1061/(ASCE)0733-9364(1983)109:4(447)
    treeJournal of Construction Engineering and Management:;1983:;Volume ( 109 ):;issue: 004
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian