Improper Detailing Results in Delayed CommissioningSource: Journal of Performance of Constructed Facilities:;1999:;Volume ( 013 ):;issue: 001Author:N. Subramanian
DOI: 10.1061/(ASCE)0887-3828(1999)13:1(29)Publisher: American Society of Civil Engineers
Abstract: A 144 m × 60 m factory building (which is the largest span in India using cold-formed steel sections) was constructed at Cochin, India. The building is made up of portal frames spanning 60 m and placed at 6 m intervals. The portal frames are supported alternately on columns and on a lattice girder that was placed longitudinally at the midspan. The portals and columns were made up of four angles, which are laced to form a box section. The lattice girder and the central column were made of 4 channels, laced to form a compound section. The building was covered with asbestos cement (AC) sheets, which are supported by cold-rolled sigma sections. The sides of the building were also covered by cladding from 1.5 m above ground level. Due to improper detailing, all the purlins and side cladding girts twisted after the AC sheets were laid, resulting in cracking of some AC sheets. In addition, diagonal sag rods were not provided in the girts and this resulted in sagging of these members. The design, detailing, and other particulars of this factory building are discussed in this paper. The solution adopted for rectifying the problems is also discussed.
|
Collections
Show full item record
| contributor author | N. Subramanian | |
| date accessioned | 2017-05-08T21:14:50Z | |
| date available | 2017-05-08T21:14:50Z | |
| date copyright | February 1999 | |
| date issued | 1999 | |
| identifier other | %28asce%290887-3828%281999%2913%3A1%2829%29.pdf | |
| identifier uri | http://yetl.yabesh.ir/yetl/handle/yetl/44174 | |
| description abstract | A 144 m × 60 m factory building (which is the largest span in India using cold-formed steel sections) was constructed at Cochin, India. The building is made up of portal frames spanning 60 m and placed at 6 m intervals. The portal frames are supported alternately on columns and on a lattice girder that was placed longitudinally at the midspan. The portals and columns were made up of four angles, which are laced to form a box section. The lattice girder and the central column were made of 4 channels, laced to form a compound section. The building was covered with asbestos cement (AC) sheets, which are supported by cold-rolled sigma sections. The sides of the building were also covered by cladding from 1.5 m above ground level. Due to improper detailing, all the purlins and side cladding girts twisted after the AC sheets were laid, resulting in cracking of some AC sheets. In addition, diagonal sag rods were not provided in the girts and this resulted in sagging of these members. The design, detailing, and other particulars of this factory building are discussed in this paper. The solution adopted for rectifying the problems is also discussed. | |
| publisher | American Society of Civil Engineers | |
| title | Improper Detailing Results in Delayed Commissioning | |
| type | Journal Paper | |
| journal volume | 13 | |
| journal issue | 1 | |
| journal title | Journal of Performance of Constructed Facilities | |
| identifier doi | 10.1061/(ASCE)0887-3828(1999)13:1(29) | |
| tree | Journal of Performance of Constructed Facilities:;1999:;Volume ( 013 ):;issue: 001 | |
| contenttype | Fulltext |