description abstractThis paper proposes a coherent risk measure to assess project cost overrun contingency reserves: the project expected cost overrun (ECO). It is shown that the traditional project cost-percentile metric does not qualify as a coherent risk measure and, therefore, that the ECO metric should be adopted. Obtained from the tail expectation of the project cost probability distribution, it measures the average value of project costs exceeding, at any significance level, the project cost baseline. A positive, unique, and exact closed-form solution to the ECO risk measure is devised under, among others, the normal probability distribution. The resulting project cost overrun contingency reserve may be interpreted as an insurance contract covering contingent risk factors and claimable by project managers from their project director once preidentified and agreed-upon contingent high-risk cost impacts are taken into account. The project ECO risk measure is extended to assess the project expected time overrun (ETO) and the project expected time overrun penalty (ETOP) risk measures, quantities that will prove indispensable for successfully tendering under any contractual form the minimum value of project time and project cost bids. They will be covering, at the very least, all relevant potential low-probability high-risk contingent risk factor impacts.
publisherASCE
titleAssessing Project Contingency Reserves with the Expected Cost Overrun Risk Measure
typeJournal Article
journal volume148
journal issue10
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/(ASCE)CO.1943-7862.0002361
journal fristpage04022102
journal lastpage04022102_11
page11
treeJournal of Construction Engineering and Management:;2022:;Volume ( 148 ):;issue: 010
contenttypeFulltext


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record