YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Cost Overruns and Formal Risk Assessment Program in US Rail Transit Projects

    Source: Journal of Construction Engineering and Management:;2020:;Volume ( 146 ):;issue: 005
    Author:
    Nan Gao
    ,
    Ali Touran
    DOI: 10.1061/(ASCE)CO.1943-7862.0001827
    Publisher: ASCE
    Abstract: Cost overrun in rail transit projects in the United States is a pervasive and constant phenomenon, yet there has been a lack of rigorous statistical analysis on project costs. This has been partly due to the difficulty of obtaining reliable cost data and the small size of the sample. In addition, the Federal Transit Administration (FTA) has required formal risk assessment on transit projects since 2003. Whether this strategy has improved the accuracy of cost estimates is not known. To fill these gaps, this study has collected the cost data of 81 US rail transit projects built during the last 40 years, the largest sample of its kind. It is found that the accuracy of cost estimates at the decision-making phase has improved over time. Also, major projects have higher percentage cost overruns than smaller projects. Further, the accuracy of cost estimates decrease as project implementation durations increase. The utilized statistical methods yielded no evidence to suggest that cost overruns differ between projects designed before and after 2003, when the FTA risk assessment program started. However, since project size and implementation duration have increased over time, the positive impact of the FTA risk assessment program can be inferred and acknowledged to some extent. This research can serve as a reference point for studies on the accuracy of conceptual cost estimates and help in budgeting future projects. It can also help in understanding the causes of cost overruns in capital projects.
    • Download: (595.2Kb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Cost Overruns and Formal Risk Assessment Program in US Rail Transit Projects

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/4268272
    Collections
    • Journal of Construction Engineering and Management

    Show full item record

    contributor authorNan Gao
    contributor authorAli Touran
    date accessioned2022-01-30T21:28:39Z
    date available2022-01-30T21:28:39Z
    date issued5/1/2020 12:00:00 AM
    identifier other%28ASCE%29CO.1943-7862.0001827.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4268272
    description abstractCost overrun in rail transit projects in the United States is a pervasive and constant phenomenon, yet there has been a lack of rigorous statistical analysis on project costs. This has been partly due to the difficulty of obtaining reliable cost data and the small size of the sample. In addition, the Federal Transit Administration (FTA) has required formal risk assessment on transit projects since 2003. Whether this strategy has improved the accuracy of cost estimates is not known. To fill these gaps, this study has collected the cost data of 81 US rail transit projects built during the last 40 years, the largest sample of its kind. It is found that the accuracy of cost estimates at the decision-making phase has improved over time. Also, major projects have higher percentage cost overruns than smaller projects. Further, the accuracy of cost estimates decrease as project implementation durations increase. The utilized statistical methods yielded no evidence to suggest that cost overruns differ between projects designed before and after 2003, when the FTA risk assessment program started. However, since project size and implementation duration have increased over time, the positive impact of the FTA risk assessment program can be inferred and acknowledged to some extent. This research can serve as a reference point for studies on the accuracy of conceptual cost estimates and help in budgeting future projects. It can also help in understanding the causes of cost overruns in capital projects.
    publisherASCE
    titleCost Overruns and Formal Risk Assessment Program in US Rail Transit Projects
    typeJournal Paper
    journal volume146
    journal issue5
    journal titleJournal of Construction Engineering and Management
    identifier doi10.1061/(ASCE)CO.1943-7862.0001827
    page11
    treeJournal of Construction Engineering and Management:;2020:;Volume ( 146 ):;issue: 005
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian