YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Environmental Laws and Their Compliance in Road Projects

    Source: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2020:;Volume ( 012 ):;issue: 001
    Author:
    Ajit K. Sinha
    ,
    Kumar Neeraj Jha
    DOI: 10.1061/(ASCE)LA.1943-4170.0000354
    Publisher: ASCE
    Abstract: There is a huge gap between the growth and demand of the road and highway sector in India. This sector carries a large percentage of freight and passengers. Before commencement of the project, obtaining environmental clearance (EC), forest clearance (FC), wildlife clearance, and coastal regulatory zone (CRZ) clearance (if required) is a necessity. Laws for environmental impact assessment study with mitigation measures and rules dealing with forest and wildlife clearance are in place. EC is granted in two stages. The second-stage approval is granted only after compliance of the conditions stipulated by the project proponents while granting Stage I approval. The paper attempts to identify the inactions that result in noncompliance with environmental laws and the reasons behind them. The methodology comprised a study of the literature followed by case studies of 12 road projects for identifying the conditions that are not complied with and the reasons for that. Finally, semistructured interviews were conducted for validation of findings. Since July 2014, the complete procedure of approval has gone online, resulting in reduction of time for granting EC from around 600 to 700 days to an average of 140 days. When the issues were discussed with experts they expressed difficulties in monitoring compliance with these conditions due to understaffing of trained personnel and nonavailability of adequate funds. The granting of EC and land acquisition both involve public hearings and therefore it has been recommended they be processed and carried out under a single window system.
    • Download: (205.7Kb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Environmental Laws and Their Compliance in Road Projects

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/4265994
    Collections
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction

    Show full item record

    contributor authorAjit K. Sinha
    contributor authorKumar Neeraj Jha
    date accessioned2022-01-30T19:47:47Z
    date available2022-01-30T19:47:47Z
    date issued2020
    identifier other%28ASCE%29LA.1943-4170.0000354.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4265994
    description abstractThere is a huge gap between the growth and demand of the road and highway sector in India. This sector carries a large percentage of freight and passengers. Before commencement of the project, obtaining environmental clearance (EC), forest clearance (FC), wildlife clearance, and coastal regulatory zone (CRZ) clearance (if required) is a necessity. Laws for environmental impact assessment study with mitigation measures and rules dealing with forest and wildlife clearance are in place. EC is granted in two stages. The second-stage approval is granted only after compliance of the conditions stipulated by the project proponents while granting Stage I approval. The paper attempts to identify the inactions that result in noncompliance with environmental laws and the reasons behind them. The methodology comprised a study of the literature followed by case studies of 12 road projects for identifying the conditions that are not complied with and the reasons for that. Finally, semistructured interviews were conducted for validation of findings. Since July 2014, the complete procedure of approval has gone online, resulting in reduction of time for granting EC from around 600 to 700 days to an average of 140 days. When the issues were discussed with experts they expressed difficulties in monitoring compliance with these conditions due to understaffing of trained personnel and nonavailability of adequate funds. The granting of EC and land acquisition both involve public hearings and therefore it has been recommended they be processed and carried out under a single window system.
    publisherASCE
    titleEnvironmental Laws and Their Compliance in Road Projects
    typeJournal Paper
    journal volume12
    journal issue1
    journal titleJournal of Legal Affairs and Dispute Resolution in Engineering and Construction
    identifier doi10.1061/(ASCE)LA.1943-4170.0000354
    page04519050
    treeJournal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2020:;Volume ( 012 ):;issue: 001
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian