YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Construction Engineering and Management
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Modified Fuzzy Group Decision-Making Approach to Cost Overrun Risk Assessment of Power Plant Projects

    Source: Journal of Construction Engineering and Management:;2019:;Volume ( 145 ):;issue: 002
    Author:
    Muhammad Saiful Islam; Madhav P. Nepal; Martin Skitmore
    DOI: 10.1061/(ASCE)CO.1943-7862.0001593
    Publisher: American Society of Civil Engineers
    Abstract: Cost overrun risk assessment in the preliminary stages of a power plant project is laden with subjectivity, uncertainty, imprecision, and the vagueness of expert judgment. Current fuzzy approaches to risk assessment in such projects specifically require improvements in the reliability and aggregation process of experts’ judgments as well as the incorporation of project phase–based risk assessment to comprehend the sources of the risks and their corresponding effects on cost overruns. In response, this study proposes a modified fuzzy group decision-making approach (FGDMA) and assesses cost overrun risks considering different project phases [(1) design and procurement, and (2) construction and commissioning] of the power plant projects of varying types, sizes/capacities, and contracts. The proposed methodology is applied to 10 different project scenarios to better understand the context of project risks and their profile and identify the critical cost overrun risks involved. This study will aid the comprehensive assessment of risks and increase the accuracy of project budgeting and contingency allocation decisions.
    • Download: (276.8Kb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Modified Fuzzy Group Decision-Making Approach to Cost Overrun Risk Assessment of Power Plant Projects

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/4254656
    Collections
    • Journal of Construction Engineering and Management

    Show full item record

    contributor authorMuhammad Saiful Islam; Madhav P. Nepal; Martin Skitmore
    date accessioned2019-03-10T12:01:07Z
    date available2019-03-10T12:01:07Z
    date issued2019
    identifier other%28ASCE%29CO.1943-7862.0001593.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4254656
    description abstractCost overrun risk assessment in the preliminary stages of a power plant project is laden with subjectivity, uncertainty, imprecision, and the vagueness of expert judgment. Current fuzzy approaches to risk assessment in such projects specifically require improvements in the reliability and aggregation process of experts’ judgments as well as the incorporation of project phase–based risk assessment to comprehend the sources of the risks and their corresponding effects on cost overruns. In response, this study proposes a modified fuzzy group decision-making approach (FGDMA) and assesses cost overrun risks considering different project phases [(1) design and procurement, and (2) construction and commissioning] of the power plant projects of varying types, sizes/capacities, and contracts. The proposed methodology is applied to 10 different project scenarios to better understand the context of project risks and their profile and identify the critical cost overrun risks involved. This study will aid the comprehensive assessment of risks and increase the accuracy of project budgeting and contingency allocation decisions.
    publisherAmerican Society of Civil Engineers
    titleModified Fuzzy Group Decision-Making Approach to Cost Overrun Risk Assessment of Power Plant Projects
    typeJournal Paper
    journal volume145
    journal issue2
    journal titleJournal of Construction Engineering and Management
    identifier doi10.1061/(ASCE)CO.1943-7862.0001593
    page04018126
    treeJournal of Construction Engineering and Management:;2019:;Volume ( 145 ):;issue: 002
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian