YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Effects of Change Orders on Cost Growth, Schedule Growth, and Construction Intensity of Large Highway Projects

    Source: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2018:;Volume ( 010 ):;issue: 003
    Author:
    Shrestha Pramen P.;Maharjan Ruiko
    DOI: 10.1061/(ASCE)LA.1943-4170.0000264
    Publisher: American Society of Civil Engineers
    Abstract: Previous research have shown that change orders have a detrimental effect on cost growth and schedule growth of construction projects. These studies mainly concentrated on the number of change orders for building or maintenance projects. However, correlation of the number and change order growth with cost growth, schedule growth, and construction intensity of new highway projects has not been studied. This study collected data from 185 projects from the state of Texas, whose costs amounted to more than $1M. The results showed that the average change order growth for these projects was 7.%, and also found a significant positive correlation in change order growth with cost growth and schedule growth of these projects. The correlation coefficients of change order growth with cost growth and schedule growth were found to be .57 and .44, respectively. When the projects were divided into two groups based on the change order growth, the results showed that the cost growth and schedule growth significantly increased as the change order growth increased to greater than 5%. The number of change orders were significantly and positively correlated with cost growth (.23), schedule growth (.3), and construction intensity (.46). When the number of change orders increased by more than 2, then the cost and schedule growth increased significantly. It is recommended that Texas Department of Transportation engineers use an effective change management process to control the change orders in their highway projects so that cost and schedule overruns could be minimized.
    • Download: (430.3Kb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Effects of Change Orders on Cost Growth, Schedule Growth, and Construction Intensity of Large Highway Projects

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/4249172
    Collections
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction

    Show full item record

    contributor authorShrestha Pramen P.;Maharjan Ruiko
    date accessioned2019-02-26T07:45:42Z
    date available2019-02-26T07:45:42Z
    date issued2018
    identifier other%28ASCE%29LA.1943-4170.0000264.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4249172
    description abstractPrevious research have shown that change orders have a detrimental effect on cost growth and schedule growth of construction projects. These studies mainly concentrated on the number of change orders for building or maintenance projects. However, correlation of the number and change order growth with cost growth, schedule growth, and construction intensity of new highway projects has not been studied. This study collected data from 185 projects from the state of Texas, whose costs amounted to more than $1M. The results showed that the average change order growth for these projects was 7.%, and also found a significant positive correlation in change order growth with cost growth and schedule growth of these projects. The correlation coefficients of change order growth with cost growth and schedule growth were found to be .57 and .44, respectively. When the projects were divided into two groups based on the change order growth, the results showed that the cost growth and schedule growth significantly increased as the change order growth increased to greater than 5%. The number of change orders were significantly and positively correlated with cost growth (.23), schedule growth (.3), and construction intensity (.46). When the number of change orders increased by more than 2, then the cost and schedule growth increased significantly. It is recommended that Texas Department of Transportation engineers use an effective change management process to control the change orders in their highway projects so that cost and schedule overruns could be minimized.
    publisherAmerican Society of Civil Engineers
    titleEffects of Change Orders on Cost Growth, Schedule Growth, and Construction Intensity of Large Highway Projects
    typeJournal Paper
    journal volume10
    journal issue3
    journal titleJournal of Legal Affairs and Dispute Resolution in Engineering and Construction
    identifier doi10.1061/(ASCE)LA.1943-4170.0000264
    page4518012
    treeJournal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2018:;Volume ( 010 ):;issue: 003
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian