YaBeSH Engineering and Technology Library

    • Journals
    • PaperQuest
    • YSE Standards
    • YaBeSH
    • Login
    View Item 
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    •   YE&T Library
    • ASCE
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
    • View Item
    • All Fields
    • Source Title
    • Year
    • Publisher
    • Title
    • Subject
    • Author
    • DOI
    • ISBN
    Advanced Search
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Archive

    Progression Analysis of the EJCDC’s Underlying Claim and Dispute Resolution Mechanism

    Source: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2018:;Volume ( 010 ):;issue: 003
    Author:
    Barakat Mohammad;Khoury Hiam;Abdul-Malak Mohamed-Asem
    DOI: 10.1061/(ASCE)LA.1943-4170.0000263
    Publisher: American Society of Civil Engineers
    Abstract: Direct negotiation is the most common approach used for cost-effective resolution of construction claims and disputes. From among the several available standard conditions of contract, those issued by the Engineers Joint Contract Documents Committee (EJCDC) call for a direct review and resolution process to be initiated immediately following the submission of a claim and supporting data by the claimant. To this effect, this paper tackles the examination of the claim process evolution under these conditions, starting with this rather long, time-barred stipulation. The used methodology relied on presenting the overall claim and dispute timeline then dissecting it in accordance with the possibilities prevailing at each of the timeline stages and their corresponding gates. Four different scenarios were identified, and their analysis revealed interesting observations along a number of characteristics. These mainly include: (1) the placement of the project owner at the forefront in deciding on actions pertaining to a contractor’s submitted claims; (2) the staging of mediation as an alternative dispute resolution means early on in the timeline as an intermittent step that can possibly be taken in lieu of, and having the effect of suspending, the direct negotiation step; and (3) the advantage given to the action by the opposing party, on one hand, and to the denial of claim by the claimant, on the other hand, in triggering expeditious closure of or in moving forward with a case on hand, respectively.
    • Download: (1.567Mb)
    • Show Full MetaData Hide Full MetaData
    • Get RIS
    • Item Order
    • Go To Publisher
    • Statistics

      Progression Analysis of the EJCDC’s Underlying Claim and Dispute Resolution Mechanism

    URI
    https://yetl.yabesh.ir/yetl1/handle/yetl/4249171
    Collections
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction

    Show full item record

    contributor authorBarakat Mohammad;Khoury Hiam;Abdul-Malak Mohamed-Asem
    date accessioned2019-02-26T07:45:42Z
    date available2019-02-26T07:45:42Z
    date issued2018
    identifier other%28ASCE%29LA.1943-4170.0000263.pdf
    identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4249171
    description abstractDirect negotiation is the most common approach used for cost-effective resolution of construction claims and disputes. From among the several available standard conditions of contract, those issued by the Engineers Joint Contract Documents Committee (EJCDC) call for a direct review and resolution process to be initiated immediately following the submission of a claim and supporting data by the claimant. To this effect, this paper tackles the examination of the claim process evolution under these conditions, starting with this rather long, time-barred stipulation. The used methodology relied on presenting the overall claim and dispute timeline then dissecting it in accordance with the possibilities prevailing at each of the timeline stages and their corresponding gates. Four different scenarios were identified, and their analysis revealed interesting observations along a number of characteristics. These mainly include: (1) the placement of the project owner at the forefront in deciding on actions pertaining to a contractor’s submitted claims; (2) the staging of mediation as an alternative dispute resolution means early on in the timeline as an intermittent step that can possibly be taken in lieu of, and having the effect of suspending, the direct negotiation step; and (3) the advantage given to the action by the opposing party, on one hand, and to the denial of claim by the claimant, on the other hand, in triggering expeditious closure of or in moving forward with a case on hand, respectively.
    publisherAmerican Society of Civil Engineers
    titleProgression Analysis of the EJCDC’s Underlying Claim and Dispute Resolution Mechanism
    typeJournal Paper
    journal volume10
    journal issue3
    journal titleJournal of Legal Affairs and Dispute Resolution in Engineering and Construction
    identifier doi10.1061/(ASCE)LA.1943-4170.0000263
    page4518010
    treeJournal of Legal Affairs and Dispute Resolution in Engineering and Construction:;2018:;Volume ( 010 ):;issue: 003
    contenttypeFulltext
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian
     
    DSpace software copyright © 2002-2015  DuraSpace
    نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
    yabeshDSpacePersian