Show simple item record

contributor authorMark J. Kaiser
contributor authorAllan G. Pulsipher
contributor authorRobert C. Byrd
date accessioned2017-05-08T21:10:27Z
date available2017-05-08T21:10:27Z
date copyrightNovember 2003
date issued2003
identifier other%28asce%290733-950x%282003%29129%3A6%28286%29.pdf
identifier urihttp://yetl.yabesh.ir/yetl/handle/yetl/41503
description abstractThe cost to decommission offshore structures in the Gulf of Mexico is examined based on 60 projects managed by Twachtman, Synder, & Byrd, Inc., over the years 1991–2001. Cost functions are established for each stage of decommissioning, including well plugging and abandonment, structure preparation, pipeline abandonment, structure removal, and site clearance and verification. The component cost of decommissioning is analyzed statistically, and regression models are empirically derived using various descriptor variables. A candid discussion of the limitations of analysis is also presented. This paper represents the first empirical study to construct decommissioning cost functions for the Gulf of Mexico region based on actual job data.
publisherAmerican Society of Civil Engineers
titleDecommissioning Cost Functions in the Gulf of Mexico
typeJournal Paper
journal volume129
journal issue6
journal titleJournal of Waterway, Port, Coastal, and Ocean Engineering
identifier doi10.1061/(ASCE)0733-950X(2003)129:6(286)
treeJournal of Waterway, Port, Coastal, and Ocean Engineering:;2003:;Volume ( 129 ):;issue: 006
contenttypeFulltext