Feasibility of a Program Delay Claims Scheme: Synergistic Effect and Risk–Cost Optimization
View/ Open
Date
2025Author
Chen, Xu
Feng, Jingchun
Zhao, Ying
Lu, Ting
Metadata
Show full item recordAbstract
AbstractIn an individual project, the delay of a contractor does not affect third parties
other than the owner. However, this is not the case for a program with multiple projects.
In this case, a delay to a previous project can cause work idleness losses ...