dc.contributor.authorRao, N. Prasad
dc.contributor.authorBalagopal, R.
dc.contributor.authorRokade, R. P.
dc.contributor.authorPalani, G. S.
dc.date.accessioned2026-08-20T12:08:55Z
dc.date.available2026-08-20T12:08:55Z
dc.date.copyright2025/03/27
dc.date.issued2025
dc.identifier.otherJSDCCC.SCENG-1721.pdf
dc.identifier.urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4313151
dc.description.abstractAbstractTransmission line (TL) towers may fail prematurely during mandatory testing for many reasons, even though they were designed based on the provisions of different standards. Five premature failures observed during full-scale testing at the Tower ...Practical ApplicationsThe reasons for the premature failure of transmission line towers during prototype testing are discussed. The reasons for failure are categorized as failure due to inadequate redundant patterns in design and failure due to improper ...
dc.publisherAmerican Society of Civil Engineers
dc.titleDetailing Redundant Pattern–Induced Failures in Transmission Line Towers
dc.typeJournal Article
dc.journal.volume30
dc.journal.issue3
dc.journal.titleJournal of Structural Design and Construction Practice
dc.identifier.doi10.1061/JSDCCC.SCENG-1721
dc.journal.fristpage04025035-1
dc.journal.lastpage04025035-12
dc.page12
dc.treeJournal of Structural Design and Construction Practice:;2025:;Volume ( 030 ):;issue: 003
dc.contenttypeFulltext