dc.contributor.authorXue, Yutong
dc.contributor.authorLe, Yun
dc.contributor.authorJia, Fuyuan
dc.contributor.authorPeng, Tong
dc.date.accessioned2026-08-20T11:49:28Z
dc.date.available2026-08-20T11:49:28Z
dc.date.copyright2025/06/05
dc.date.issued2025
dc.identifier.otherJMENEA.MEENG-6726.pdf
dc.identifier.urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4312720
dc.description.abstractAbstractThe timely and high-quality transition to operations for large infrastructure projects (LIPs) requires an integrated schedule of construction and operational readiness, which is inherently vulnerable to multiple risks. These risks cause delays in ...
dc.publisherAmerican Society of Civil Engineers
dc.titleDelays in Large Infrastructure Projects Transitioning to Operations: Analysis Based on a Schedule–Risk Network Coupling Model
dc.typeJournal Article
dc.journal.volume41
dc.journal.issue5
dc.journal.titleJournal of Management in Engineering
dc.identifier.doi10.1061/JMENEA.MEENG-6726
dc.journal.fristpage04025035-1
dc.journal.lastpage04025035-21
dc.page21
dc.treeJournal of Management in Engineering:;2025:;Volume ( 041 ):;issue: 005
dc.contenttypeFulltext