    Toward Better Applicability of Public Procurement Law: Delay Claims by the Contractor and Limit of Compensation under the Performance Guarantee

    Thumbnail
    View/Open
    %28ASCE%29LA.1943-4170.0000490.pdf (211.4Kb)
    Date
    11/1/2021
    Author
    Amr Abu Helw
    A. Samer Ezeldin
    Metadata
    Show full item record
    Abstract
    Contracts between government and private entities are a daily occurrence. The administrative contracts are concluded by selecting the private partner by the public authority, through the means provided by the law such as tenders, auction, and direct negotiation. Such contracts are governed by the national public procurement law of the country. The term public procurement law relates to those legal provisions and legitimate arrangements that control the purchasing and procuring of works, services, and goods by the government, institutions, and public bodies. These include, among others, ministries, public enterprises, municipalities, and city councils. On October 3, 2018, a new Egyptian public procurement, namely, Law No. 182 of 2018, was issued to regulate contracts concluded by public authorities. The executive regulation of the law was issued on October 31, 2019. This paper presents a set of proposed amendments to the law, in line with relevant laws in many countries of the world, standard forms of contracts, and court rules to make it more equitable and to avoid unbalanced provisions that make international contractors and investors refrain from dealing with major projects in Egypt. The suggested amendments address two specific subjects, delay claims by the contractor and the limit of compensation under performance guarantee.
    URI
    http://yetl.yabesh.ir/yetl1/handle/yetl/4272434
    Collections
    • Journal of Legal Affairs and Dispute Resolution in Engineering and Construction

    DSpace software copyright © 2002-2015  DuraSpace
    Contact Us | Send Feedback
    Theme by 
    @mire NV
     

     

    Browse

    All of DSpaceCommunities & CollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

    My Account

    LoginRegister

    Statistics

    View Usage Statistics

    DSpace software copyright © 2002-2015  DuraSpace
    Contact Us | Send Feedback
    Theme by 
    @mire NV