dc.description.abstractBundled wind–thermal generation system (BWTGS) is an effective way to utilize remote large–scale wind power. The optimal generation maintenance schedule (GMS) for BWTGS is not only helpful to improve the system reliability level but also useful to enhance the system economic efficiency and extend the lifetime of components. This paper presents a model to optimize the GMS for BWTGS. The probabilistic production simulation technique is employed to calculate the system costs, and a sequential probabilistic method is utilized to capture the sequential and stochastic nature of wind power. A hybrid optimization algorithm (HOA) based on the simulated annealing (SA) and multipopulation parallel genetic algorithm (GA) is developed to solve the proposed model. Case studies demonstrate the effectiveness of this proposed model. Effects of the reliability deterioration of thermal generating units (TGUs) and the pattern of BWTGS transmission power are also investigated.
dc.publisherThe American Society of Mechanical Engineers (ASME)
dc.titleOptimal Generation Maintenance Schedule for Bundled Wind–Thermal Generation System
dc.typeJournal Paper
dc.journal.volume140
dc.journal.issue1
dc.journal.titleJournal of Energy Resources Technology
dc.identifier.doi10.1115/1.4037536
dc.journal.fristpage14501
dc.journal.lastpage014501-7
dc.treeJournal of Energy Resources Technology:;2018:;volume 140:;issue 001
dc.contenttypeFulltext


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record