dc.contributor.authorClifford L. Truitt
dc.contributor.authorJames E. Clausner
dc.contributor.authorT. Neil McLellan
dc.date.accessioned2017-05-08T21:09:23Z
dc.date.available2017-05-08T21:09:23Z
dc.date.copyrightNovember 1989
dc.date.issued1989
dc.identifier.other%28asce%290733-950x%281989%29115%3A6%28741%29.pdf
dc.identifier.urihttp://yetl.yabesh.ir/yetl/handle/yetl/40778
dc.description.abstractCapping is the controlled, accurate placement of contaminated dredged material at a disposal site which is covered by a cap of clean isolating material. Capping projects are typically categorized as either level‐bottom placement or contained aquatic disposal. Field experience with subaqueous capping is limited, but 11 sites have been identified where the technique has been applied. Site selection considerations for capping projects are similar to those for any open‐water disposal. The influences of several site characteristics on capping have been identified and discussed. Modeling methods are available to aid in evaluating sites and designs. Additional information on cap materials, placement, and monitoring techniques are provided.
dc.publisherAmerican Society of Civil Engineers
dc.titleConsiderations for Capping Subaqueous Dredged Material Deposits
dc.typeJournal Paper
dc.journal.volume115
dc.journal.issue6
dc.journal.titleJournal of Waterway, Port, Coastal, and Ocean Engineering
dc.identifier.doi10.1061/(ASCE)0733-950X(1989)115:6(741)
dc.treeJournal of Waterway, Port, Coastal, and Ocean Engineering:;1989:;Volume ( 115 ):;issue: 006