description abstractThe decisions made during the preproject planning and design stages are very crucial for infrastructure and underground projects due to the inherent risks and uncertainties in such projects. In the selection of a crossing method, the owner has to consider various factors, including cost, environmental impact, serviceability and maintenance, constructability, and schedule. Unfortunately, this decision is complex due to the numerous variables that need to be considered. When choosing a crossing methodology, the project manager must balance the likely capital cost of the project with the risks inherent in the chosen construction method. Ideally, a project manager would investigate numerous alternatives to fully explore the merits of various construction methods, including the level of risk, before making the final decision. This paper presents the results of an actual project workshop with the objective of selecting the most optimum construction method for the construction of a water transmission main beneath the North Saskatchewan River, in Edmonton, Alberta, Canada. The project used the analytical hierarchy process as a method to capture the risks, merits, and demerits of each construction method. Conventional open trench, horizontal directional drilling, microtunneling, and conventional tunneling were the four methods considered for the project. The paper includes the background information, workshop setting, methodology of the selection criteria, and the results of the workshop considered in selecting the most optimum method for the specific project circumstances. A summary of the design based on the recommended methodology is also presented along with a summary of the crossing construction completed in 2007.
publisherAmerican Society of Civil Engineers
titleAnalytical Decision Analysis for Construction Methodology Selection for a Water Transmission Main River Crossing
typeJournal Paper
journal volume6
journal issue1
journal titleJournal of Pipeline Systems Engineering and Practice
identifier doi10.1061/(ASCE)PS.1949-1204.0000119
treeJournal of Pipeline Systems Engineering and Practice:;2015:;Volume ( 006 ):;issue: 001
contenttypeFulltext


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record