description abstractThis study compares the performance of design/bid/build and design/build to see if one project delivery method is superior in regards to time and cost. Similar military buildings were used to identify two samples of projects delivered with each of the two delivery methods. These projects provide a meaningful comparison because they include buildings of the same typology (i.e., U.S. Navy Bachelor Enlisted Quarters) delivered using similar design models. Project duration, project duration per bed, project time growth, cost growth and cost per bed were statistically compared. Upon completion of the analysis, the hypothesis that design/build projects are superior to design/bid/build projects in regards to time and cost was tested. Design/build projects were proven superior in performance in almost every measure. Other findings, including recommendations to practitioners and researchers, will be provided as well.
publisherAmerican Society of Civil Engineers
titleEmpirical Comparison of Design/Build and Design/Bid/Build Project Delivery Methods
typeJournal Paper
journal volume135
journal issue7
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/(ASCE)CO.1943-7862.0000017
treeJournal of Construction Engineering and Management:;2009:;Volume ( 135 ):;issue: 007