description abstractActivity duration is uncertain due to the variation in the outside environment, such as weather, site congestion, productivity level, etc. Furthermore, resources for construction activities are limited in the real construction world so that scheduling must include resource allocation. A new optimal resource-constrained construction scheduling model is proposed in this paper, in which the effects of both uncertain activity duration and resource constraints are taken into account. Fuzzy set theory is used to model the uncertainties of activity duration. A genetic algorithm-based searching technique is adopted to search for the fuzzy optimal project duration under resource constraints. The model can effectively provide the optimal fuzzy profiles of project duration and resource amounts under the constraint of limited resources.
publisherAmerican Society of Civil Engineers
titleFuzzy Optimal Model for Resource-Constrained Construction Scheduling
typeJournal Paper
journal volume13
journal issue3
journal titleJournal of Computing in Civil Engineering
identifier doi10.1061/(ASCE)0887-3801(1999)13:3(207)
treeJournal of Computing in Civil Engineering:;1999:;Volume ( 013 ):;issue: 003
contenttypeFulltext


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record