contributor authorHarun Turkoglu
contributor authorDavid Arditi
contributor authorGul Polat
date accessioned2024-04-27T22:46:38Z
date available2024-04-27T22:46:38Z
date issued2024/05/01
identifier other10.1061-JCEMD4.COENG-14314.pdf
identifier urihttp://yetl.yabesh.ir/yetl1/handle/yetl/4297469
description abstractThis study proposes an optimization model based on particle swarm optimization (PSO) to achieve the objectives of minimizing project duration, project cost, and resource fluctuation while maximizing project quality and schedule flexibility. The objectives of this study are as follows: (1) to determine whether the interrelationships between these five objectives affect the outcome of the optimization; (2) to determine whether the presence or absence of resource constraints affects the solution; and (3) to verify that the solution of the PSO-based optimization model coincides with the exact mathematical solution, but faster. An example project was presented to illustrate the applicability of the proposed model. The conclusions of this study are as follows: (1) multiple objectives do interact with each other and should be evaluated simultaneously rather than one at a time to reach realistic solutions, (2) resource constraints do affect the solutions obtained, and (3) the proposed model successfully reaches an optimal solution that is extremely close to the exact mathematical solution much faster than the mathematical model.
publisherASCE
titleAugmented Time–Cost Trade-Off Optimization Using Particle Swarm Optimization
typeJournal Article
journal volume150
journal issue5
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/JCEMD4.COENG-14314
journal fristpage04024031-1
journal lastpage04024031-13
page13
treeJournal of Construction Engineering and Management:;2024:;Volume ( 150 ):;issue: 005
contenttypeFulltext