description abstractThe earth pressure balance (EPB) shield has proven to be successful for tunneling in soft ground in homogeneous soils. On three recent soft ground tunneling projects in Washington, D.C., EPB shields were used in mixed ground conditions with a high water table. Many areas were found with sands in the crown, and clays in the invert. In a limited number of cases, silicate grouting was used in the sands as a measure to provide extra control for ground movements. Ground conditions were found to play a major role in the observed response. Sticky, stiff clays caused problems with movement of muck through the bulkhead and conveyor system. Movement data showed that the tunneling consistently caused large ground settlements in those areas with sands over clays where no chemical grouting was performed. Movements were well controlled in instances with clays in the crown or where the sands were chemically grouted.
publisherAmerican Society of Civil Engineers
titleEPB Shield Tunneling in Mixed Face Conditions
typeJournal Paper
journal volume119
journal issue10
journal titleJournal of Geotechnical Engineering
identifier doi10.1061/(ASCE)0733-9410(1993)119:10(1640)
treeJournal of Geotechnical Engineering:;1993:;Volume ( 119 ):;issue: 010