description abstractThe well-known earned value technique measures and evaluates project performance. It uncovers schedule and cost deviations from the baseline plan. However, it is not established to determine acceptable levels of deviations from the baseline. This study applies the Shewhart individuals control charts to overcome this limitation; the charts monitor trends in the project performance behavior and allow them to be detected before the project deviates much from the baseline plan. The study statistically monitors several well-known earned value indexes of a construction project, where the data are autocorrelated and nonnormally distributed. The investigated case showed that the individuals control charts enhance capability of the earned value technique. The authors concluded that implementing the developed tool together with the traditional tools noticeably improves the project controlling scheme and provides more information on project progress. The study extends a previous study in which only independent data were investigated.
publisherAmerican Society of Civil Engineers
titleLessons Learned from Applying the Individuals Control Charts to Monitoring Autocorrelated Project Performance Data
typeJournal Paper
journal volume142
journal issue5
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/(ASCE)CO.1943-7862.0001078
treeJournal of Construction Engineering and Management:;2016:;Volume ( 142 ):;issue: 005
contenttypeFulltext


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record