description abstractA model for project budgeting and scheduling with uncertainty is developed. The traditional critical-path method (CPM) misleads because there are few, if any, real-life deterministic situations for which CPM is a great match; program evaluation and review technique (PERT) has been seen to have its problems, too (e.g., merge bias, unavailability of data, difficulty of implementation by practitioners). A dual focus on the distributions of the possible errors in the time and cost estimates and on the reliability of the estimates used as planned values suggests an approach for developing reliable schedules and budgets with buffers for time and cost. This method for budgeting and scheduling is executed through either simulation or a simple analytical approximation. The dynamic buffers provide much-needed flexibility, accounting for the errors in cost and duration estimates associated with planning any real project, thus providing a realistic, practical, and dynamic approach to planning and scheduling.
publisherAmerican Society of Civil Engineers
titleUncertainty in Task Duration and Cost Estimates: Fusion of Probabilistic Forecasts and Deterministic Scheduling
typeJournal Paper
journal volume139
journal issue5
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/(ASCE)CO.1943-7862.0000616
treeJournal of Construction Engineering and Management:;2013:;Volume ( 139 ):;issue: 005
contenttypeFulltext


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record