contributor authorBrad W. Wambeke
contributor authorMin Liu
contributor authorSimon M. Hsiang
date accessioned2017-05-08T21:39:35Z
date available2017-05-08T21:39:35Z
date copyrightApril 2012
date issued2012
identifier other%28asce%29co%2E1943-7862%2E0000451.pdf
identifier urihttp://yetl.yabesh.ir/yetl/handle/yetl/58606
description abstractVariation, defined for this research as the time difference between what was planned and what actually happened, is important as it can affect the productivity performance of construction tasks. The construction process is complex and consists of a large number of interdependent tasks. When the starting time and/or duration of one task varies, it can affect other downstream tasks and result in disruptions to the schedule and/or decreased productivity. This research examined the effect of using a risk assessment matrix in conjunction with the Last Planner System (LPS) method to reduce and/or eliminate task duration variation. A case study was conducted involving a mechanical contractor who specializes in plumbing, heating, ventilation, and air conditioning. The company compared the performance of two separate, but similar projects. The LPS method was used with one of the projects and the company’s traditional planning system was used with the other (i.e., not using the LPS system). A total of 16 weeks’ worth of data was collected for each project. Variation, productivity, and cost savings were analyzed using a risk assessment matrix and benefit–cost procedures. The project that used the LPS method had a 35% higher productivity performance than the traditionally planned project and resulted in a benefit–cost ratio of
publisherAmerican Society of Civil Engineers
titleUsing Last Planner and a Risk Assessment Matrix to Reduce Variation in Mechanical Related Construction Tasks
typeJournal Paper
journal volume138
journal issue4
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/(ASCE)CO.1943-7862.0000444
treeJournal of Construction Engineering and Management:;2012:;Volume ( 138 ):;issue: 004