description abstractSchedule conformance depends on construction activities starting and finishing on time. However, construction activities are often delayed because construction flows necessary to start their execution are unavailable. Construction flows can be classified into: labor, equipment, workspace, materials, precedence, information, and external. Current construction models do not formally represent, measure, and track all flow types. Hence, field managers lack formal methods for managing flows and instead rely on their intuition and experience managing them. This paper presents a construction model based on activities and flows called the activity–flow model (AFM). The AFM formally represents the activities, the flows, and their interactions. The AFM was validated prospectively through its implementation on three building projects that were in different phases (foundations, core and shell, and finishing), at different geographic locations (Bogota, Copenhagen, and Lima), and used different planning and control methods (master schedule and weekly planning, last planner system, and location-based management system). The AFM was able to represent all the activities and flows in the test projects, track variations of activities and flows, and quantify activity and flow variability. Field managers can use the metrics enabled by the AFM to plan and control the project. Such proactive flow management can help field managers improve flow readiness, which should reduce activity delays and improve schedule conformance.
publisherASCE
titleManaging On-Site Production Using an Activity and Flow–Based Construction Model
typeJournal Article
journal volume150
journal issue1
journal titleJournal of Construction Engineering and Management
identifier doi10.1061/JCEMD4.COENG-13643
journal fristpage04023144-1
journal lastpage04023144-14
page14
treeJournal of Construction Engineering and Management:;2024:;Volume ( 150 ):;issue: 001
contenttypeFulltext


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record